290 Infiltration Wells Have been Made in East Jakarta Along January to September

Of the target of 500 wells, 290 have been completed and the rest are targeted to be complete in the upcoming November

The East Jakarta Water Resources (SDA) Sub-agency has noted that as many as 290 infiltration wells have been made along January to September.

Puryanto. Division Head of Maintenance said that its development was realized in ten sub-districts.

Jatinegara SDA Targets to Build 20 Wells in Cipinang Muara

"Of the target of 500 wells, 290 have been completed and the rest are targeted to be complete in the upcoming November," he expressed, Wednesday (9/12).

By doing so, it could minimize flooding in the region.

Linked News
Popular News indeks
  1. South Jakarta Keeps Anticipating Potential for Inundation and Flooding

    access_time17-04-2024 remove_red_eye717 personTiyo Surya Sakti
  2. Water Channel Being Constructed on Pramuka Island

    access_time18-04-2024 remove_red_eye568 personAnita Karyati
  3. 1,999 Homecomers Arrive at Pulogebang Terminal This Morning

    access_time16-04-2024 remove_red_eye531 personNurito
  4. Duren Sawit Community Health Center Served 300 Patients on Eid Holidays

    access_time16-04-2024 remove_red_eye500 personNurito
  5. City - Sojitz Corporation Cooperate to Speed Up MRT 2A Phase

    access_time18-04-2024 remove_red_eye393 personFolmer