 Pengerjaan Pemasangan Sheetpile Kali BGR Capai 45 Persen

December, Sheetpile Installation in KBR River Completed

The sheetpile installation process on the BGR River, Kelapa Gading Barat Urban Village, Kelapa Gading, North Jakarta has reached 45 percent.

The work includes two sides of the river and has reached 45 percent. Each east and west side covers 950 meters

Andika Purnomo, Section Head of Development and Improvement for East Flow River and Coast Systems stated that sheetpile is developed up to 1,900 meters length. It has been carried out since July 2018.

Sheetpile Slide in Bidara Cina Pump House

"The work includes two sides of the river and has reached 45 percent. Each east and west side covers 950 meters," he expressed, Monday (10/29).

It is an effort to overcome inundation that often occurs on Jalan Boulevard Barat during rainy season. In the future, at the end of the river, there will be a pump house to flow water to Sunter River.

"Yet its pump procurement is not this year. Temporarily we will make a bend first. Our target the work can be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1422 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1364 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1273 personFolmer
  4. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1072 personNurito
  5. Jakarta KPU Records More Than 8.2 Million Registered Voters

    access_time06-07-2026 remove_red_eye1003 personFolmer