 Pengerjaan Pemasangan Sheetpile Kali BGR Capai 45 Persen

December, Sheetpile Installation in KBR River Completed

The sheetpile installation process on the BGR River, Kelapa Gading Barat Urban Village, Kelapa Gading, North Jakarta has reached 45 percent.

The work includes two sides of the river and has reached 45 percent. Each east and west side covers 950 meters

Andika Purnomo, Section Head of Development and Improvement for East Flow River and Coast Systems stated that sheetpile is developed up to 1,900 meters length. It has been carried out since July 2018.

Sheetpile Slide in Bidara Cina Pump House

"The work includes two sides of the river and has reached 45 percent. Each east and west side covers 950 meters," he expressed, Monday (10/29).

It is an effort to overcome inundation that often occurs on Jalan Boulevard Barat during rainy season. In the future, at the end of the river, there will be a pump house to flow water to Sunter River.

"Yet its pump procurement is not this year. Temporarily we will make a bend first. Our target the work can be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye751 personFakhrizal Fakhri
  2. Jakarta Regional Budget Spending Reaches Rp10.38 Trillion in Q1

    access_time17-04-2026 remove_red_eye697 personDessy Suciati
  3. Job Absorption Rises in Jakarta

    access_time17-04-2026 remove_red_eye598 personDessy Suciati
  4. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye590 personTiyo Surya Sakti
  5. Training and Certification Boost Tourism Workforce Competitiveness

    access_time17-04-2026 remove_red_eye573 personAldi Geri Lumban Tobing