 Pengerjaan Pemasangan Sheetpile Kali BGR Capai 45 Persen
.
photo Budhi Firmansyah Surapati - Beritajakarta.id

December, Sheetpile Installation in KBR River Completed

The sheetpile installation process on the BGR River, Kelapa Gading Barat Urban Village, Kelapa Gading, North Jakarta has reached 45 percent.

The work includes two sides of the river and has reached 45 percent. Each east and west side covers 950 meters

Andika Purnomo, Section Head of Development and Improvement for East Flow River and Coast Systems stated that sheetpile is developed up to 1,900 meters length. It has been carried out since July 2018.

Sheetpile Slide in Bidara Cina Pump House

"The work includes two sides of the river and has reached 45 percent. Each east and west side covers 950 meters," he expressed, Monday (10/29).

It is an effort to overcome inundation that often occurs on Jalan Boulevard Barat during rainy season. In the future, at the end of the river, there will be a pump house to flow water to Sunter River.

"Yet its pump procurement is not this year. Temporarily we will make a bend first. Our target the work can be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Most Residents Satisfied with Pramono-Rano's Performance

    access_time25-06-2025 remove_red_eye312 personDessy Suciati
  2. Pramono Ensures KJP will Continue to Be Distributed

    access_time26-06-2025 remove_red_eye309 personDessy Suciati
  3. No Car Free Day on June 29 to Support Jakarta International Marathon 2025

    access_time24-06-2025 remove_red_eye283 personAldi Geri Lumban Tobing
  4. 19,675 People Visit Ragunan Zoo on Islamic New Year

    access_time27-06-2025 remove_red_eye275 personTiyo Surya Sakti
  5. Here are Parking Spaces around Lapangan Banteng for Jakarta's Anniversary

    access_time21-06-2025 remove_red_eye270 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik