 Pengerjaan Pemasangan Sheetpile Kali BGR Capai 45 Persen

December, Sheetpile Installation in KBR River Completed

The sheetpile installation process on the BGR River, Kelapa Gading Barat Urban Village, Kelapa Gading, North Jakarta has reached 45 percent.

The work includes two sides of the river and has reached 45 percent. Each east and west side covers 950 meters

Andika Purnomo, Section Head of Development and Improvement for East Flow River and Coast Systems stated that sheetpile is developed up to 1,900 meters length. It has been carried out since July 2018.

Sheetpile Slide in Bidara Cina Pump House

"The work includes two sides of the river and has reached 45 percent. Each east and west side covers 950 meters," he expressed, Monday (10/29).

It is an effort to overcome inundation that often occurs on Jalan Boulevard Barat during rainy season. In the future, at the end of the river, there will be a pump house to flow water to Sunter River.

"Yet its pump procurement is not this year. Temporarily we will make a bend first. Our target the work can be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1786 personFakhrizal Fakhri
  2. Jakarta Assesses Needs and Coordinates Aid for NTT Earthquake Victims

    access_time16-08-2026 remove_red_eye734 personAldi Geri Lumban Tobing
  3. Pramono: Independence must Be Manifested Through Concrete Action

    access_time17-08-2026 remove_red_eye684 personDessy Suciati
  4. Jakarta Prepares Aid for NTT Earthquake Victims

    access_time16-08-2026 remove_red_eye683 personDessy Suciati
  5. Pramono Commends Madurese Community for Their Vital Role in Building Jakarta

    access_time19-08-2026 remove_red_eye656 personDessy Suciati