 Pengerjaan Pemasangan Sheetpile Kali BGR Capai 45 Persen
.
photo Budhi Firmansyah Surapati - Beritajakarta.id

December, Sheetpile Installation in KBR River Completed

The sheetpile installation process on the BGR River, Kelapa Gading Barat Urban Village, Kelapa Gading, North Jakarta has reached 45 percent.

The work includes two sides of the river and has reached 45 percent. Each east and west side covers 950 meters

Andika Purnomo, Section Head of Development and Improvement for East Flow River and Coast Systems stated that sheetpile is developed up to 1,900 meters length. It has been carried out since July 2018.

Sheetpile Slide in Bidara Cina Pump House

"The work includes two sides of the river and has reached 45 percent. Each east and west side covers 950 meters," he expressed, Monday (10/29).

It is an effort to overcome inundation that often occurs on Jalan Boulevard Barat during rainy season. In the future, at the end of the river, there will be a pump house to flow water to Sunter River.

"Yet its pump procurement is not this year. Temporarily we will make a bend first. Our target the work can be complete by the end of this year," he hoped.

Linked News
Popular News indeks
  1. 1,262 Personnel Ready to Support Bhayangkara Anniversary Cleanliness

    access_time30-06-2025 remove_red_eye584 personAldi Geri Lumban Tobing
  2. 4,072 Damaged Roads in Central Jakarta Have Been Repaired

    access_time04-07-2025 remove_red_eye358 personFolmer
  3. Dishub Pushes Digitization of Parking Management for Local Revenue

    access_time01-07-2025 remove_red_eye298 personFakhrizal Fakhri
  4. Pramono Asks for Onrust Island Tourism Potential to Be Optimized

    access_time04-07-2025 remove_red_eye248 personDessy Suciati
  5. Transjabodetabek Bekasi-Galunggung Route Officially Operates

    access_time03-07-2025 remove_red_eye247 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik