Pengerjaan Sheet Pile Tanggul Kali Pesanggrahan Capai 70 Persen

Sheet Pile Construction of Pesanggrahan River Reaches 70 Percent

Jakarta Water Resources Agency keeps anticipating flood in the capital. One of the efforts is constructing sheet pile on Pesanggrahan Riverbank, Kedoya Selatan Urban Village, Kebon Jeruk Sub-district, West Jakarta.

It is targeted to complete in March 2024

Sub-agency's Drainage Sub-coordinator, Firmansyah Saputra, said the progress has reached 70 percent.

"The sheet pile is constructed on segment of Jalan Kedoya Raya up to Jalan Puri Kembangan," he said, Friday (2/16).

Two Weeks, Repair of Channels on Jalan Pluit Sakti 1 Completed

According to him, the sheet pile is installed along 1,000 meter of the west side of Pesanggrahan River on Jalan Haji Briti, Kembangan Selatan Urban Village.

Firman hoped the sheet pile construction will handle the overflow of Pesanggrahan River on Jalan Haji Briti and its surrounding.

"It is targeted to complete in March 2024," he closed.

Linked News
Popular News indeks
  1. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye420 personDessy Suciati
  2. 10,000 Participants Join People's Sports Festival at Velodrome

    access_time04-10-2026 remove_red_eye360 personNurito
  3. Kelapa Gading-Pulogadung Link Road Targeted for Completion in 2027

    access_time09-10-2026 remove_red_eye348 personDessy Suciati
  4. Moving Day, Apuran River Locals Clear Out for New Flood Pump

    access_time09-10-2026 remove_red_eye343 personBudhi Firmansyah Surapati
  5. Public Health Alert, Jakarta Urged to Anticipate Influenza A Surge

    access_time07-10-2026 remove_red_eye340 personFakhrizal Fakhri