Pengerjaan Sheet Pile Tanggul Kali Pesanggrahan Capai 70 Persen
....
photo Istimewa - Beritajakarta.id

Sheet Pile Construction of Pesanggrahan River Reaches 70 Percent

Jakarta Water Resources Agency keeps anticipating flood in the capital. One of the efforts is constructing sheet pile on Pesanggrahan Riverbank, Kedoya Selatan Urban Village, Kebon Jeruk Sub-district, West Jakarta.

It is targeted to complete in March 2024

Sub-agency's Drainage Sub-coordinator, Firmansyah Saputra, said the progress has reached 70 percent.

"The sheet pile is constructed on segment of Jalan Kedoya Raya up to Jalan Puri Kembangan," he said, Friday (2/16).

Two Weeks, Repair of Channels on Jalan Pluit Sakti 1 Completed

According to him, the sheet pile is installed along 1,000 meter of the west side of Pesanggrahan River on Jalan Haji Briti, Kembangan Selatan Urban Village.

Firman hoped the sheet pile construction will handle the overflow of Pesanggrahan River on Jalan Haji Briti and its surrounding.

"It is targeted to complete in March 2024," he closed.

Linked News
Popular News indeks
  1. W. Jakarta Bina Marga Sub-agency Repairs Kembangan Outer Ring Road Section

    access_time07-05-2024 remove_red_eye501 personTP Moan Simanjuntak
  2. Jakarta Takes Part in Arabian Travel Market 2024 in Dubai

    access_time08-05-2024 remove_red_eye411 personAldi Geri Lumban Tobing
  3. Tengah Urban Village PPSU Personnel Clean Fire Debris

    access_time10-05-2024 remove_red_eye389 personNurito
  4. Jalan YRS III Repairs in South Jakarta Completed

    access_time10-05-2024 remove_red_eye378 personTiyo Surya Sakti
  5. 35 Toddlers in Kedoya Selatan Received Assistance with Nutritious Additional Food

    access_time13-05-2024 remove_red_eye371 personTP Moan Simanjuntak