Pengerjaan Sheet Pile Tanggul Kali Pesanggrahan Capai 70 Persen

Sheet Pile Construction of Pesanggrahan River Reaches 70 Percent

Jakarta Water Resources Agency keeps anticipating flood in the capital. One of the efforts is constructing sheet pile on Pesanggrahan Riverbank, Kedoya Selatan Urban Village, Kebon Jeruk Sub-district, West Jakarta.

It is targeted to complete in March 2024

Sub-agency's Drainage Sub-coordinator, Firmansyah Saputra, said the progress has reached 70 percent.

"The sheet pile is constructed on segment of Jalan Kedoya Raya up to Jalan Puri Kembangan," he said, Friday (2/16).

Two Weeks, Repair of Channels on Jalan Pluit Sakti 1 Completed

According to him, the sheet pile is installed along 1,000 meter of the west side of Pesanggrahan River on Jalan Haji Briti, Kembangan Selatan Urban Village.

Firman hoped the sheet pile construction will handle the overflow of Pesanggrahan River on Jalan Haji Briti and its surrounding.

"It is targeted to complete in March 2024," he closed.

Linked News
Popular News indeks
  1. Jakarta Calls on Residents to Save Energy with 60-Minute Lights-Off Action

    access_time19-09-2026 remove_red_eye424 personAldi Geri Lumban Tobing
  2. Jakarta International Stadium Sets Up Transit Schemes for The Weeknd Concert

    access_time24-09-2026 remove_red_eye399 personAldi Geri Lumban Tobing
  3. South Jakarta BPBD Distributes 44,000 Liters of Clean Water

    access_time19-09-2026 remove_red_eye360 personTiyo Surya Sakti
  4. Indonesia-Singapore Match: 80 Dishub Personnel Deployed to Manage Traffic Around GBK

    access_time25-09-2026 remove_red_eye353 personAldi Geri Lumban Tobing
  5. Jakarta Inspectorate Partners with KPK to Foster Early Anti-Corruption Culture

    access_time20-09-2026 remove_red_eye307 personFolmer