Normalisasi Ciliwung Baru 47 Persen
.
photo Nurito - Beritajakarta.id

Ciliwung River Normalization Reaches 47 Percent

The normalization project for Ciliwung river along 19 kilometer has reached 47 percent. Flat availability for relocated citizens must be prepared as soon as possible.

The building demolishment should be postponed since the flat is not ready yet

The Public Works and Public Housing Ministry's Ciliwung-Cisadane Flood Control Office (BBWSCC) head T. Iskandar, said that the project is still working in Kampung Pulo up to Kampung Melayu and Bidaracina. He hoped the project will touch Bukit Duri and Kebon Manggis as soon as the citizens are relocated.

“The building demolishment should be postponed since the flat is not ready yet,” he said, Monday (2/1).

Bukit Duri Residents Remain Relocated

His side will intensify the coordination with East Jakarta and South Jakarta Administration related to building demolishment at Ciliwung riverbank. It is hoped many flats will available in next June.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye526 personBudhi Firmansyah Surapati
  2. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye434 personAldi Geri Lumban Tobing
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye408 personDessy Suciati
  4. S. Jakarta Mayor: Idul Adha is a Moment to Enhance Compassion Among One Another

    access_time06-06-2025 remove_red_eye294 personTiyo Surya Sakti
  5. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye277 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik