Ciliwung River Normalization Reaches 47 Percent

The normalization project for Ciliwung river along 19 kilometer has reached 47 percent. Flat availability for relocated citizens must be prepared as soon as possible.

The building demolishment should be postponed since the flat is not ready yet

The Public Works and Public Housing Ministry's Ciliwung-Cisadane Flood Control Office (BBWSCC) head T. Iskandar, said that the project is still working in Kampung Pulo up to Kampung Melayu and Bidaracina. He hoped the project will touch Bukit Duri and Kebon Manggis as soon as the citizens are relocated.

“The building demolishment should be postponed since the flat is not ready yet,” he said, Monday (2/1).

Bukit Duri Residents Remain Relocated

His side will intensify the coordination with East Jakarta and South Jakarta Administration related to building demolishment at Ciliwung riverbank. It is hoped many flats will available in next June.

Linked News
Popular News indeks
  1. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye680 personDessy Suciati
  2. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye510 personAldi Geri Lumban Tobing
  3. Jakarta Builds Five New Animal Health Centers to Expand Veterinary Services

    access_time30-09-2026 remove_red_eye506 personAldi Geri Lumban Tobing
  4. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye481 personFakhrizal Fakhri
  5. 1,500 Runners and Pets Hit the Track for World Rabies Day Run 2026

    access_time03-10-2026 remove_red_eye473 personAnita Karyati