 Pembongkaran Jembatan Kalibata Terkendala Kiriman Sampah

Dismantling of Kalibata Bridge Stagnated

Dismantling process of Kalibata Bridge, Rawajatim, Pancoran, South Jakarta had to be postponed and wait for garbage transportation under bridge is completed.

The problem is floodwater and garbage from Bogor, thus we have to do dredging first and continued with dismantling," he told, Wednesday (3/9).

Implementer of Dismantling in Kalibata Bridge, Iksan Masduki said one unit of breaker should work interchangeably with one unit of backhoe to pick up garbage from Ciliwung River.

Kalibata Bridge Demolished

"The problem is floodwater and garbage from Bogor, thus we have to do dredging first and continued with dismantling," he told, Wednesday (3/9).

He expressed, such dismantling is predicted to be complete within 15 days ahead.

Linked News
Popular News indeks
  1. Fire at Pondok Bambu Allegedly Triggered by Electrical Short

    access_time19-05-2026 remove_red_eye1389 personNurito
  2. Governor Pramono Named Vice Chair of C40 Cities Steering Committee

    access_time18-05-2026 remove_red_eye1022 personAldi Geri Lumban Tobing
  3. Kultura Market in Pademangan Barat Attracts Crowds

    access_time22-05-2026 remove_red_eye869 personAnita Karyati
  4. Inundation on DI Panjaitan Road Recede

    access_time20-05-2026 remove_red_eye849 personNurito
  5. Dharma Jaya Ready for Thousands of Eid al-Adha Sacrifices

    access_time20-05-2026 remove_red_eye661 personAldi Geri Lumban Tobing