You don't have javascript enabled. Good luck with that.
Pencarian
Pengerjaan Breakwater Di Tiga Pulau Permukiman Terus Dikebut

Breakwater Project in Seribu Islands Accelerated

The breakwater project in the waters of Panggang, Pramuka and Karya islands, Seribu Islands keeps being accelerated.

Our hope is we could finish it within three months

"From nine residential islands, construction process of the breakwater in three islands out of them is faster," said Head of Seribu Islands Water Management Sub-dept, Mustajab, Thursday (7/20).

Due to varied long, the construction progress is surely different. In details, the breakwater long in Panggang Islands is about 594 meters, Pramuka Island with 594 meters and Karya Island with 369 meters.

Breakwater in Seribu Islands must Be Tested

"Our hope is we could finish it within three months," he hoped.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2403 personDessy Suciati
  2. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye790 personTiyo Surya Sakti
  3. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye697 personDessy Suciati
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye636 personTiyo Surya Sakti
  5. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye520 personNurito