Jalur Layang MRT Masuk Tahap Pemasangan Gelagar
.
photo Istimewa - Beritajakarta.id

MRT Flyover Lane Enters Girder Installation

Mass Rapid Transit (MRT) flyover lane corridor at Jalan Sisingamaraja enter the girder installation. Girder installation target completion from Jalan Sisingamaraja heading to Haji Nawi is by the mid of 2017.

Daily target is six girders. Working hour is from 10 PM to 4 AM

PT MRT Jakarta Director, Dono Bustami, said the installation is part of MRT flyover lane construction.

“Daily target is six girders. Working hour is from 10 PM to 4 AM,” he said, Wednesday (8/10).

Second-Phase MRT Project Completed This Year

Box girder to be installed is produced by Wika Beton-Jaya Beton Joint Operation. CP 103 package contract is handled by Obayashi-Shimizu-Jaya Konstruksi Joint Venture (OSJ JV).

“Girder installation at CP 103 has two launching gantry devices that will be used for route Jalan Sisingamaraja up to Jalan Fatmawati,” he closed.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1045 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye908 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye553 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye450 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye386 personAldi Geri Lumban Tobing