Jalur Layang MRT Masuk Tahap Pemasangan Gelagar
.
photo Istimewa - Beritajakarta.id

MRT Flyover Lane Enters Girder Installation

Mass Rapid Transit (MRT) flyover lane corridor at Jalan Sisingamaraja enter the girder installation. Girder installation target completion from Jalan Sisingamaraja heading to Haji Nawi is by the mid of 2017.

Daily target is six girders. Working hour is from 10 PM to 4 AM

PT MRT Jakarta Director, Dono Bustami, said the installation is part of MRT flyover lane construction.

“Daily target is six girders. Working hour is from 10 PM to 4 AM,” he said, Wednesday (8/10).

Second-Phase MRT Project Completed This Year

Box girder to be installed is produced by Wika Beton-Jaya Beton Joint Operation. CP 103 package contract is handled by Obayashi-Shimizu-Jaya Konstruksi Joint Venture (OSJ JV).

“Girder installation at CP 103 has two launching gantry devices that will be used for route Jalan Sisingamaraja up to Jalan Fatmawati,” he closed.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye533 personBudhi Firmansyah Surapati
  2. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye517 personAldi Geri Lumban Tobing
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye421 personDessy Suciati
  4. S. Jakarta Mayor: Idul Adha is a Moment to Enhance Compassion Among One Another

    access_time06-06-2025 remove_red_eye336 personTiyo Surya Sakti
  5. North Jakarta Mayor Ensures Basic Needs of Kapuk Muara Fire Victims Are Met

    access_time07-06-2025 remove_red_eye299 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik