Channel Project at Jalan Rorotan V Still Reaches 50 Percent
access_time August 11 2016 02:23 PM remove_red_eye 1493
Reported by Aldi Geri Lumban Tobing | Translated by Rizky Mawardi
Reported by Aldi Geri Lumban Tobing | Translated by Rizky Mawardi
North Jakarta Sub-dept. of Water Management provides water channel at Jalan Rorotan V RW 05, Rorotan Urban Village, Cilincing. The channel length is 323 meters.
The water can not flow due to no water channel
Since the early construction in July, now the process has reached 50 percent or 135 meters.
North Jakarta Head Sub-dept. of Water Management, Herning Wahyuningsih, said the channel project is based on local citizens request. The area is always flooded by 30 cm during rainy season.
Channel & Conduit Around Presidential Palace Cleaned“The water can not flow due to no water channel,” she said, Wednesday (8/10).
According to her, the project is targeted to complete in September