Jalan Kebon Jahe VII Channel Normalized
access_time August 30 2016 11:03 AM remove_red_eye 1449
Reported by Rudi Hermawan | Translated by Rizky Mawardi
Reported by Rudi Hermawan | Translated by Rizky Mawardi
Water channel along Jalan Kebon Jahe VII, Petojo Selatan, Gambir, is normalized by Central Jakarta Sub-dept. of Water Management. The effort is aimed to widen the channel.
Previous wide was 40 cm and depth was 40 cm. We’ll widen up to 60 cm and 80 cm of depth
Head Section of Maintenance for the agency, Boris Karlop Lumbangaol, said the project has been started since August 22 ago. It is hoped the channel volume will be able to accommodate water during heavy rain.
“Previous wide was 40 cm and depth was 40 cm. We’ll widen up to 60 cm and 80 cm of depth,” he said, Monday (8/29).
Water Channel at Jalan Puspa Raya CleanedHis side deploys 15 personnel everyday. It is targeted the project to complete in October 2016.
“Project is run in 45 days or complete in October,” he added.