Renovasi 45 Sekolah Gagal Lelang Sebab Waktu Tak Cukup
.
photo Yopie Oscar - Beritajakarta.id

Limited Time, 45 Schools Renovation Failed

Of 83 schools to be renovated, only 38 schools can go. The remaining 45 schools auction are failed due to limited time.

We must cancel the plan since the time left is 3.5 months

Jakarta Head Dept. of Education, Sopan Adrianto, said the auction result was announced in August. It means his side only has 3.5 months left.

“We must cancel the plan since the time left is 3.5 months,” he said, Monday (9/5).

Council Wants School Building Renovation Continued

Not only about the matter of time, the cancellation is also based on school access. Narrow access made the heavy equipments can not enter the location.

“Manual construction will take longer time,” he added.

According to him, the allocated budget this year is Rp 1.04 trillion. Rp 471 billion will be used to renovate 38 schools, and the remaining Rp 571 trillion is returned to the regional cash.

“The 45 schools renovation will be proposed again next year,” he closed.

Linked News
Popular News indeks
  1. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye415 personBudhi Firmansyah Surapati
  2. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye398 personFolmer
  3. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye355 personTiyo Surya Sakti
  4. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye325 personAldi Geri Lumban Tobing
  5. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye317 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik