Renovasi 45 Sekolah Gagal Lelang Sebab Waktu Tak Cukup
.
photo Yopie Oscar - Beritajakarta.id

Limited Time, 45 Schools Renovation Failed

Of 83 schools to be renovated, only 38 schools can go. The remaining 45 schools auction are failed due to limited time.

We must cancel the plan since the time left is 3.5 months

Jakarta Head Dept. of Education, Sopan Adrianto, said the auction result was announced in August. It means his side only has 3.5 months left.

“We must cancel the plan since the time left is 3.5 months,” he said, Monday (9/5).

Council Wants School Building Renovation Continued

Not only about the matter of time, the cancellation is also based on school access. Narrow access made the heavy equipments can not enter the location.

“Manual construction will take longer time,” he added.

According to him, the allocated budget this year is Rp 1.04 trillion. Rp 471 billion will be used to renovate 38 schools, and the remaining Rp 571 trillion is returned to the regional cash.

“The 45 schools renovation will be proposed again next year,” he closed.

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye950 personTP Moan Simanjuntak
  2. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye654 personBudhi Firmansyah Surapati
  3. Satpol PP Expels Illegal Participants at Sudirman - Thamrin CFD

    access_time27-10-2024 remove_red_eye454 personBudhi Firmansyah Surapati
  4. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye394 personTiyo Surya Sakti
  5. Traffic Arrangement Applied on Jalan Tambak

    access_time28-10-2024 remove_red_eye370 personAldi Geri Lumban Tobing