Peningkatan Pendestrian di Jatibaru Sudah 55 Persen

Jatibaru Sidewalk Elevation Project Reaches 55 Percent

The improvement and construction of sidewalk at Jalan Jatibaru, Tanah Abang has reached 55 percent. Jakarta Dept. of Bina Marga targets to complete the project by October.

It is targeted to complete in October

“Now the project has reached 55 percent,” said Ricky Janus, Head Section of Development for Road Infrastructures and Utility (KPJJU) Dept. of Bina Marga, Friday (9/9).

He added that sidewalk improvement along 950 meters and 4.5 to 6 meters width is based on the lane availability.

Sidewalk, Park, and Road Arrangement Must Run Together

“It is targeted to complete in October. The project has touched Tanah Abang Station,” he added.

Moreover, the sidewalk is already equipped with ducting box. It will ease third party installing fiber optic cables.

“Ducting box is targeted to complete by December. There are 90 boxes. Each box has its own ID,” he closed.

Linked News
Popular News indeks
  1. Check Saturday's Traffic Diversions for Jakarta Running Festival

    access_time23-10-2026 remove_red_eye955 personAldi Geri Lumban Tobing
  2. MRT Jakarta Prolongs Weekend Service for Kanye West Concert

    access_time23-10-2026 remove_red_eye859 personAldi Geri Lumban Tobing
  3. MRT Jakarta Modifies Schedule for Jakarta Running Festival

    access_time23-10-2026 remove_red_eye845 personAldi Geri Lumban Tobing
  4. Pramono Praises JRF, Says City Is Becoming a Trusted Event Host

    access_time23-10-2026 remove_red_eye688 personDessy Suciati
  5. Jakarta Records Improved Air Quality on First Day of JRF 2026

    access_time24-10-2026 remove_red_eye669 personBudhi Firmansyah Surapati