Normalisasi Ciliwung di Bukit Duri Dikebut

Ciliwung River Normalization in Bukit Duri Accelerated

The normalization of Ciliwung River in Bukit Duri, Tebet, South Jakarta is accelerated. At this moment, pole installation for sheet pile at the river has reached 1,300 meters.

Total execution is targeted in December

It is targeted that the installation along 2,000 meters will complete December 2016.

“Total execution is targeted in December,” said Teuku Iskandar, BBWSCC Head, Monday (10/31).

Illegal Buildings at Krukut Riverbank Controlled

After installing the sheet pile, his side will install parapet wall along 2,000 meters. According to him, the normalization project has no problem so far.

“We’ll also install sheet pile along 700 meters at Gang Arus Cawang, Kramat Jati. Heavy equipments have been prepared at the site,” he closed.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1424 personFolmer
  2. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye859 personAldi Geri Lumban Tobing
  3. Commemorating Vesak, Jakarta Lights Up with Illumination of Jakarta 2026

    access_time30-05-2026 remove_red_eye658 personBudhi Firmansyah Surapati
  4. Seniors Participate in Pasti Bisa Berkarya at MRT Stations

    access_time02-06-2026 remove_red_eye611 personAldi Geri Lumban Tobing
  5. Krendang Fire Victims Receive Proper Support and Assistance

    access_time29-05-2026 remove_red_eye479 personBudhi Firmansyah Surapati