Normalisasi Ciliwung di Bukit Duri Dikebut
.
photo Nurito - Beritajakarta.id

Ciliwung River Normalization in Bukit Duri Accelerated

The normalization of Ciliwung River in Bukit Duri, Tebet, South Jakarta is accelerated. At this moment, pole installation for sheet pile at the river has reached 1,300 meters.

Total execution is targeted in December

It is targeted that the installation along 2,000 meters will complete December 2016.

“Total execution is targeted in December,” said Teuku Iskandar, BBWSCC Head, Monday (10/31).

Illegal Buildings at Krukut Riverbank Controlled

After installing the sheet pile, his side will install parapet wall along 2,000 meters. According to him, the normalization project has no problem so far.

“We’ll also install sheet pile along 700 meters at Gang Arus Cawang, Kramat Jati. Heavy equipments have been prepared at the site,” he closed.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye526 personBudhi Firmansyah Surapati
  2. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye396 personDessy Suciati
  3. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye390 personAldi Geri Lumban Tobing
  4. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye271 personAldi Geri Lumban Tobing
  5. S. Jakarta Mayor: Idul Adha is a Moment to Enhance Compassion Among One Another

    access_time06-06-2025 remove_red_eye270 personTiyo Surya Sakti

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik