Pembebasan Lahan MRT Ditargetkan Rampung Desember
.
photo Reza Hapiz - Beritajakarta.id

MRT Land Buying Process Targeted to Complete December

The construction of MRT Lebak Bulus-Bundaran Hotel Indonesia route phase 1 is still disturbed by land buying process. Now, several land owners have agreed with the loan-use agreement. It is targeted to complete the land buying in December.

Our problem is for 127 land lots. I think it can be solved in mid December

Acting Jakarta Governor, Sumarsono, said 281 land lots need to be bought, but only 127 are priorities. The budget has been prepared in 2016 city budget.

“Our problem is for 127 land lots. I think it can be solved in mid December,” he said, Tuesday (11/15).

Acting Governor Satisfied with Progress of MRT Project

The budget has been prepared in Dept. of Bina Marga and Dept. of Transportation. He hoped the project will finish on time since it is a national project. If this project is complete, second phase Bundaran HI-Kampung Bandan (Ancol TImur) construction can be run.

“So let’s support the program for our pride too,” he closed.

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye954 personTP Moan Simanjuntak
  2. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye660 personBudhi Firmansyah Surapati
  3. Satpol PP Expels Illegal Participants at Sudirman - Thamrin CFD

    access_time27-10-2024 remove_red_eye454 personBudhi Firmansyah Surapati
  4. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye395 personTiyo Surya Sakti
  5. Traffic Arrangement Applied on Jalan Tambak

    access_time28-10-2024 remove_red_eye370 personAldi Geri Lumban Tobing