Pembebasan Lahan MRT Ditargetkan Rampung Desember

MRT Land Buying Process Targeted to Complete December

The construction of MRT Lebak Bulus-Bundaran Hotel Indonesia route phase 1 is still disturbed by land buying process. Now, several land owners have agreed with the loan-use agreement. It is targeted to complete the land buying in December.

Our problem is for 127 land lots. I think it can be solved in mid December

Acting Jakarta Governor, Sumarsono, said 281 land lots need to be bought, but only 127 are priorities. The budget has been prepared in 2016 city budget.

“Our problem is for 127 land lots. I think it can be solved in mid December,” he said, Tuesday (11/15).

Acting Governor Satisfied with Progress of MRT Project

The budget has been prepared in Dept. of Bina Marga and Dept. of Transportation. He hoped the project will finish on time since it is a national project. If this project is complete, second phase Bundaran HI-Kampung Bandan (Ancol TImur) construction can be run.

“So let’s support the program for our pride too,” he closed.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1578 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1437 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1301 personFolmer
  4. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1094 personNurito
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye965 personDessy Suciati