Pembebasan Lahan MRT Ditargetkan Rampung Desember
.
photo Reza Hapiz - Beritajakarta.id

MRT Land Buying Process Targeted to Complete December

The construction of MRT Lebak Bulus-Bundaran Hotel Indonesia route phase 1 is still disturbed by land buying process. Now, several land owners have agreed with the loan-use agreement. It is targeted to complete the land buying in December.

Our problem is for 127 land lots. I think it can be solved in mid December

Acting Jakarta Governor, Sumarsono, said 281 land lots need to be bought, but only 127 are priorities. The budget has been prepared in 2016 city budget.

“Our problem is for 127 land lots. I think it can be solved in mid December,” he said, Tuesday (11/15).

Acting Governor Satisfied with Progress of MRT Project

The budget has been prepared in Dept. of Bina Marga and Dept. of Transportation. He hoped the project will finish on time since it is a national project. If this project is complete, second phase Bundaran HI-Kampung Bandan (Ancol TImur) construction can be run.

“So let’s support the program for our pride too,” he closed.

Linked News
Popular News indeks
  1. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye414 personBudhi Firmansyah Surapati
  2. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye395 personFolmer
  3. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye352 personTiyo Surya Sakti
  4. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye324 personAldi Geri Lumban Tobing
  5. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye316 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik