Pembebasan Lahan MRT Ditargetkan Rampung Desember
.
photo Reza Hapiz - Beritajakarta.id

MRT Land Buying Process Targeted to Complete December

The construction of MRT Lebak Bulus-Bundaran Hotel Indonesia route phase 1 is still disturbed by land buying process. Now, several land owners have agreed with the loan-use agreement. It is targeted to complete the land buying in December.

Our problem is for 127 land lots. I think it can be solved in mid December

Acting Jakarta Governor, Sumarsono, said 281 land lots need to be bought, but only 127 are priorities. The budget has been prepared in 2016 city budget.

“Our problem is for 127 land lots. I think it can be solved in mid December,” he said, Tuesday (11/15).

Acting Governor Satisfied with Progress of MRT Project

The budget has been prepared in Dept. of Bina Marga and Dept. of Transportation. He hoped the project will finish on time since it is a national project. If this project is complete, second phase Bundaran HI-Kampung Bandan (Ancol TImur) construction can be run.

“So let’s support the program for our pride too,” he closed.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1503 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye924 personAldi Geri Lumban Tobing
  3. Residents Flock to Cheap Bazaar at Cilandak Timur Urban Village Office

    access_time15-01-2025 remove_red_eye771 personTiyo Surya Sakti
  4. City and Kejati Forge Cooperation for Good Government Governance

    access_time21-01-2025 remove_red_eye388 personFolmer
  5. 13 Inter-village Bridges in South Jakarta Revitalized

    access_time16-01-2025 remove_red_eye367 personTiyo Surya Sakti