Housing Agency Targets 60 Percent of Budget Realization
access_time November 30 2016 04:34 PM remove_red_eye 1781
Reported by Jhon Syah Putra Kaban | Translated by Rizky Mawardi
Reported by Jhon Syah Putra Kaban | Translated by Rizky Mawardi
The budget realization of Dept. of Public Housing and Governmental Building only reaches 30 percent out of total budget Rp 1.4 trillion. It is predicted that the realization will only reach 60 percent up to the end of this year.
Budget realization is low due to several programs realization also low. Our target is only 60 percent
“Budget realization is low due to several programs realization also low. Our target is only 60 percent,” said Arifin, agency’s head, Wednesday (11/30).
The unfinished programs are City Hall Block F renovation. The asset deletion takes 88 days.
Until November, Cleanliness Dept's Budget Absorption Reached 44.1 Percent“Next is seven flats construction. Two contractors contract was cut and five others are temporarily cut,” he added.
Next year, his side allocates Rp 4 trillion to finish the incomplete programs including the construction of 24 flat towers.
“The flat construction will be in Nagrak, Penggilingan, Pulo Gebang, Polri Pesing, and Rorotan,” he closed.