Education Agency Proposes Time Extension for School Construction
access_time December 15 2016 02:50 PM remove_red_eye 1371
Reported by Folmer | Translated by Rizky Mawardi
Reported by Folmer | Translated by Rizky Mawardi
Jakarta Dept. of Education proposes time extension for five out of 38 school construction projects which were using 2016 city budget.
The projects are SDN 06-09 Penjaringan, SDN 11-12 Pejagalan, SMPN 162, 244 and 266
The effort is taken since the projects only reach 90 percent by December 30, 2016.
“The projects are SDN 06-09 Penjaringan, SDN 11-12 Pejagalan, SMPN 162, 244 and 266,” said Sopan Adrianto, agency’s head, Wednesday (12/14).
Construction of SMPN 143 DelayedBased on the assessment, the project will finish on January 15, 2017. The SDN 15 and 22 Klender, East Jakarta will complete this month.
“The contractor has promised to complete the project by this month,” he added.
The remaining 33 projects of school building in Jakarta will complete before next year.