Becakayu Toll Section 1 Targeted Finish May 2017
Reported by Budhi Firmansyah Surapati | Translated by Maria Inggita
Bekasi-Cawang-Kampung Melayu (Becakayu) Toll Section 1 access starts from Bekasi to Cipinang Mall, Duren Sawit, is targeted to operate in May 2017. The progress has already touched 85.386 percent.
15 percent of total section 1 not freed yet. It is from Pasar Gembrong to Cipinang Mall and from Cipinang Mall to Pangkalan Jati
PT. Kresna Kusuma Dyandra Marga (KKDM) Technical Director, Dwi Pratikno said that overall, Becakayu Toll Section 1 has 11.5 kilometers long. This access starts from Jaka Sampurna (West Bekasi) to Kampung Melayu with 5 points of exit and entrance gates. Section 1 is targeted to finish gradually until end of 2017.
While Section 2 starts from Jaka Sampurna (West Bekasi) to Duren Jaya (East Bekasi) for about 21.5 kilometers long.
E. Jakarta Administration to Cooperate with Becakayu Contractor"15 percent of total section 1 is not bought yet. It is from Pasar Gembrong to Cipinang Mall and from Cipinang Mall to Pangkalan Jati," he said, Thursday (1/19).
Dwi explained, if land acquisition can finish this January, he optimistic that toll from section 2 to Cipinang Mall can operate next May.