Simpang Susun Semanggi Masuki Tahap Penyambungan Konstruksi

Semanggi Interchanges Enters Connecting Progress

Semanggi Interchanges enters crucial phase, that is connecting phase which located above City inner toll for ramp 1, Grogol-Blok M lane.

Today, President and Governor have seen connecting progress for ramp 1

Jakarta Bina Marga Dept. Head, Yusmada Faizal, said that connection phase above toll for ramp 1 was started since February 21, 2017.

"President and Governor have seen connecting progress for ramp 1," said Yusmada in Semanggi Interchanges project location, South Jakarta, Thursday (2/23).

Jokowi Wants Semanggi Interchanges Finishes On Time

He added the construction above toll is targeted to be done on next March 11. While for Polda-Bundaran HI has not entering connecting progress above toll yet.

"Later on, both of them will be connected above toll," he expressed.

According to him, all construction progress have reached 60 percent, 6 percent faster from original target.

"Semanggi Interchange is targeted to be finished in August next year," he closed.

For information, Semanggi Interchanges construction is budgeted Rp 360 billion. It uses budget from developer proposing compensation for adding building floor coefficient (KLB).

Linked News
Popular News indeks
  1. Jakarta Set to Launch Historic Municipal Bonds, Pramono Says

    access_time01-07-2026 remove_red_eye1171 personDessy Suciati
  2. Jakarta Government Quickly Addresses Toddler Falling into a Hole Incident

    access_time29-06-2026 remove_red_eye673 personDessy Suciati
  3. Central Jakarta Offers Free Tattoo Removal Service to 100 Residents

    access_time29-06-2026 remove_red_eye537 personFolmer
  4. Asylum Seekers Urged Not to Occupy Public Facilities Outside UNHCR Office

    access_time02-07-2026 remove_red_eye521 personTiyo Surya Sakti
  5. Jakarta Prepares 11 New Housing Projects for Better Living

    access_time30-06-2026 remove_red_eye506 personFakhrizal Fakhri