You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan Waduk Cimanggis Sudah 20 Persen
.
photo Istimewa - Beritajakarta.id

Cimanggis Reservoir Construction Reaches 20 Percent

Cimanggis Reservoir construction progress, Cibubur, Ciracas, East Jakarta recently already has reached 20 percent.

Now we focus on wet sectional area. Overall construction has reached around 20 percent

Jakarta Water Resources Dept.'s East Flow Field Head, Ahmad Syaiful, said the construction has been started since 2 months ago. There are 5 units of excavator deployed daily to dredge the site.

"Now we focus on wet sectional area. Overall construction has reached around 20 percent," he said, Thursday (3/9).

Setu Reservoir Proposed to Be Tourism Site

He explained that this reservoir will be equipped with water gates, spill way, connecting channel, and inspection road. Hopefully, the construction will be finished in November.

"Right now, all lands have been bought. Hopefully, can be finished as target," he closed.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1210 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1053 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye907 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye734 personFolmer
  5. Jakarta Provincial Government Holds Christmas Carol

    access_time18-12-2024 remove_red_eye578 personDessy Suciati