Pembangunan Waduk Cimanggis Sudah 20 Persen
.
photo Istimewa - Beritajakarta.id

Cimanggis Reservoir Construction Reaches 20 Percent

Cimanggis Reservoir construction progress, Cibubur, Ciracas, East Jakarta recently already has reached 20 percent.

Now we focus on wet sectional area. Overall construction has reached around 20 percent

Jakarta Water Resources Dept.'s East Flow Field Head, Ahmad Syaiful, said the construction has been started since 2 months ago. There are 5 units of excavator deployed daily to dredge the site.

"Now we focus on wet sectional area. Overall construction has reached around 20 percent," he said, Thursday (3/9).

Setu Reservoir Proposed to Be Tourism Site

He explained that this reservoir will be equipped with water gates, spill way, connecting channel, and inspection road. Hopefully, the construction will be finished in November.

"Right now, all lands have been bought. Hopefully, can be finished as target," he closed.

Linked News
Popular News indeks
  1. Deputy Gov Rano: Meat Stocks Secured Up to Ramadhan

    access_time22-02-2025 remove_red_eye560 personBudhi Firmansyah Surapati
  2. Jakarta to Hold Cheap Food Bazaar at 193 Locations

    access_time22-02-2025 remove_red_eye455 personBudhi Firmansyah Surapati
  3. Pramono - Rano Expected to Realize Better Resident Welfare

    access_time20-02-2025 remove_red_eye310 personBudhi Firmansyah Surapati
  4. Jakartans Invited to Participate in HPSN 2025 Event

    access_time21-02-2025 remove_red_eye303 personAldi Geri Lumban Tobing
  5. 41 Wild Cats in Cikoko Sterilized

    access_time21-02-2025 remove_red_eye297 personTiyo Surya Sakti