Ciliwung Sodetan Construction Has Touched 54.7 Percent

This is a must, water from Ciliwung can be flowed into KBT

The construction of Ciliwung crossing channel (sodetan) that functions to flow water from Ciliwung River towards East Flood Canal (KBT) has reached 54.7 percent or 600 meters out of 1.27 kilometers.

City Secretary, Saefullah asserted the construction is very urgent to overcome flood problem.

Crossing to Be Provided at Rawa Babon Reservoir

"This is a must, water from Ciliwung can be flowed into KBT," he stated, Monday (4/3).

According to him, the KBT capacity is very adequate to flow water towards the upstream or the sea.

"Hopefully, the sodetan construction and Ciliwung normalization can be recontinued soon," he stated.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye528 personBudhi Firmansyah Surapati
  2. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye491 personAldi Geri Lumban Tobing
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye415 personDessy Suciati
  4. S. Jakarta Mayor: Idul Adha is a Moment to Enhance Compassion Among One Another

    access_time06-06-2025 remove_red_eye326 personTiyo Surya Sakti
  5. North Jakarta Mayor Ensures Basic Needs of Kapuk Muara Fire Victims Are Met

    access_time07-06-2025 remove_red_eye287 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik