Pembangunan Sky Hospital RSUD Tarakan Capai 23 Persen

Tarakan RSUD Sky Hospital Construction Has Reached 23 Percent

Sky Hospital building construction of Tarakan Public Hospital (RSUD), Cideng, Central Jakarta has reached 23 percent.

Currently it reaches 23 percent. It is still on schedule

The construction is targeted to finish on December 20.

Tarakan RSUD Director, Togi Asman Sinaga said, Sky Hospital building construction is on schedule. His side is optimistic this construction can be finished on time, in accordance to contract.

Tarakan RSUD Construction Begins

"Currently it reaches 23 percent. It is still on schedule," he said at City Council Building, Tuesday (8/15).

He explained, there is budget savings in this construction. Previous allocated budget was Rp 309 billion. But the auction winner offered 87 percent from total budget.

"So, there is budget savings. In contract, construction cost is Rp 263 billion. But contractor is capable just with 87 percent from the allocated budget," he said.

According to him, Tarakan RSUD Sky Hospital building inauguration will be held in January 2018. Jakarta Provincial Government will add 120 beds plus its completed facilities and service in this type A RSUD.

Linked News
Popular News indeks
  1. 129 Motorcycle Parked Illegally in Daan Mogot Controlled

    access_time08-11-2026 remove_red_eye711 personBudhi Firmansyah Surapati
  2. Kampung Melayu Sports Facility Inaugurated to Tackle Brawls

    access_time06-11-2026 remove_red_eye670 personDessy Suciati
  3. Jakarta to Develop Its First Mangrove Botanical Garden

    access_time06-11-2026 remove_red_eye666 personDessy Suciati
  4. Aid for Fire Survivors at Pinus Elok Flats Has Been Distributed

    access_time06-11-2026 remove_red_eye634 personNurito
  5. Kampung Rambutan 1 Reservoir to Combine Flood Control with Public Recreation

    access_time06-11-2026 remove_red_eye630 personAldi Geri Lumban Tobing