Pembangunan Velodrome dan Equistrian Park Masih Sesuai Target
.
photo istimewa - Beritajakarta.id

Construction of Velodrome and Equestrian Park Accelerated

The construction of Rawamangun Velodrome and Pulomas Equestrian Park, East Jakarta keeps being accelerated. 

Thus far, the deviation of the project is still positive, likewise with Light Rail Transit (LRT) is still on progress

Jakarta Youth and Sports Dept. Head, Ratiyono disclosed, until end of August, the deviation of the Equestrian and Velodrome construction is still positive. Hence, his dept. believes it will be right on target.

"Thus far, the deviation of the project is still positive, likewise with Light Rail Transit (LRT) is still on progress," he stated, Sunday (8/27).

Empty Billboards can Be Used for Asian Games Socialization

He explained, the Velodrome project has reached 45 percent. As for Equestrian project has reached 50 percent.

"Equestrian is hoped to be finished by the end of November or early December and Velodrome in March, 2018," he finished.

Linked News
Popular News indeks
  1. Pramono Prioritizes Construction of Cakung Regional Hospital

    access_time18-04-2025 remove_red_eye469 personFakhrizal Fakhri
  2. Governor Pramono Joins Cycling in Jakarta Silaturahride 2025

    access_time19-04-2025 remove_red_eye409 personBudhi Firmansyah Surapati
  3. Jakarta to Make Public Transportation Free on April 24, 2025

    access_time18-04-2025 remove_red_eye321 personAldi Geri Lumban Tobing
  4. City Goverment Encourages Residents to Use Public Transportation

    access_time21-04-2025 remove_red_eye284 personFakhrizal Fakhri
  5. Transjakarta Applies Special Fares for Female Customers

    access_time20-04-2025 remove_red_eye266 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik