Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. East Jakarta Satpol PP Deployed to Ensure Safe Eid Travel Period

    access_time16-03-2026 remove_red_eye650 personNurito
  2. Governor Attends Melasti Ceremony at Segara Temple

    access_time15-03-2026 remove_red_eye559 personBudhi Firmansyah Surapati
  3. Pramono Inaugurates 26 Home Renovation Units

    access_time16-03-2026 remove_red_eye411 personDessy Suciati
  4. Travelers Departing from Lebak Bulus Terminal Starting to Increase

    access_time13-03-2026 remove_red_eye312 personTiyo Surya Sakti
  5. Jakarta Planetarium Rolls Out Varied Shows for Eid al-Fitr Holiday

    access_time11-03-2026 remove_red_eye307 personAldi Geri Lumban Tobing