Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. Transjabodetabek PIK 2-Blok M Route Serves 1.4 Million Passengers

    access_time24-05-2026 remove_red_eye1843 personAldi Geri Lumban Tobing
  2. West Jakarta to Host Career Day Walk-in Interviews Next Week

    access_time21-05-2026 remove_red_eye1159 personBudhi Firmansyah Surapati
  3. Kultura Market in Pademangan Barat Attracts Crowds

    access_time22-05-2026 remove_red_eye1126 personAnita Karyati
  4. Commission E Pushes for Evaluation of Free Private School Program

    access_time25-05-2026 remove_red_eye706 personFakhrizal Fakhri
  5. Jakarta Government Hosts Jakarta Sales Mission in China

    access_time25-05-2026 remove_red_eye701 personAldi Geri Lumban Tobing