Normalisasi Saluran Penghubung Malakasari Mencapai 450 Meter
.
photo Suparni - Beritajakarta.id

Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye543 personFolmer
  2. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye477 personDessy Suciati
  3. Foul Smell Around JGC Clarified Not Coming from Rorotan RDF

    access_time28-03-2025 remove_red_eye418 personAldi Geri Lumban Tobing
  4. City Submits 2024 Financial Report to BPK

    access_time26-03-2025 remove_red_eye356 personBudhi Firmansyah Surapati
  5. Residents Hope Another Free Homecoming Program Held Next Year

    access_time27-03-2025 remove_red_eye308 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik