Normalisasi Saluran Penghubung Malakasari Mencapai 450 Meter

Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. Jakarta Calls on Residents to Save Energy with 60-Minute Lights-Off Action

    access_time19-09-2026 remove_red_eye423 personAldi Geri Lumban Tobing
  2. Jakarta International Stadium Sets Up Transit Schemes for The Weeknd Concert

    access_time24-09-2026 remove_red_eye392 personAldi Geri Lumban Tobing
  3. South Jakarta BPBD Distributes 44,000 Liters of Clean Water

    access_time19-09-2026 remove_red_eye359 personTiyo Surya Sakti
  4. Indonesia-Singapore Match: 80 Dishub Personnel Deployed to Manage Traffic Around GBK

    access_time25-09-2026 remove_red_eye318 personAldi Geri Lumban Tobing
  5. Jakarta Inspectorate Partners with KPK to Foster Early Anti-Corruption Culture

    access_time20-09-2026 remove_red_eye307 personFolmer