photo Suparni - Beritajakarta.id

Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. Deputy Gov Rano: Meat Stocks Secured Up to Ramadhan

    access_time22-02-2025 remove_red_eye557 personBudhi Firmansyah Surapati
  2. Jakarta to Hold Cheap Food Bazaar at 193 Locations

    access_time22-02-2025 remove_red_eye451 personBudhi Firmansyah Surapati
  3. Pramono - Rano Expected to Realize Better Resident Welfare

    access_time20-02-2025 remove_red_eye309 personBudhi Firmansyah Surapati
  4. Jakartans Invited to Participate in HPSN 2025 Event

    access_time21-02-2025 remove_red_eye301 personAldi Geri Lumban Tobing
  5. 41 Wild Cats in Cikoko Sterilized

    access_time21-02-2025 remove_red_eye296 personTiyo Surya Sakti