Normalisasi Saluran Penghubung Malakasari Mencapai 450 Meter

Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1018 personNurito
  2. Jakarta KPU Records More Than 8.2 Million Registered Voters

    access_time06-07-2026 remove_red_eye940 personFolmer
  3. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye825 personDessy Suciati
  4. MRT Phase 2A Northbound Tunnel Excavation Completed

    access_time09-07-2026 remove_red_eye696 personAldi Geri Lumban Tobing
  5. Addressing Collapsed Road in Pulo Gadung is a Priority, Pramono Says

    access_time08-07-2026 remove_red_eye677 personDessy Suciati