Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. BMKG: Sunny to Cloudy Skies Forecast Across Jakarta Today

    access_time11-09-2026 remove_red_eye1707 personDessy Suciati
  2. Jakarta Reallocates Funds for Rp 250M Suckermouth Catfish Study After Pramono’s Direct Order

    access_time10-09-2026 remove_red_eye701 personFakhrizal Fakhri
  3. Pramono Urges Jakmania to Keep Jakarta Safe

    access_time11-09-2026 remove_red_eye461 personDessy Suciati
  4. Pramono Endorses Five-City Tour for Jazz Goes to Campus

    access_time12-09-2026 remove_red_eye441 personDessy Suciati
  5. No Damage Reported Following Magnitude 5.9 Seribu Islands Quake

    access_time12-09-2026 remove_red_eye430 personBudhi Firmansyah Surapati