Normalisasi Saluran Penghubung Malakasari Mencapai 450 Meter

Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. Jakarta Set to Launch Historic Municipal Bonds, Pramono Says

    access_time01-07-2026 remove_red_eye1117 personDessy Suciati
  2. Night at The Library Marks Jakarta's 499th Anniversary with Five-Century Message

    access_time27-06-2026 remove_red_eye791 personAnita Karyati
  3. Transportation Agency Teams Up with Ride-Hailing Driver Communities to Promote Road Safety

    access_time27-06-2026 remove_red_eye673 personAldi Geri Lumban Tobing
  4. Jakarta Primed for Transformation into a World-Class Global Hub

    access_time28-06-2026 remove_red_eye634 personDessy Suciati
  5. Jakarta Government Quickly Addresses Toddler Falling into a Hole Incident

    access_time29-06-2026 remove_red_eye629 personDessy Suciati