You don't have javascript enabled. Good luck with that.
Pencarian
Normalisasi Saluran Penghubung Malakasari Mencapai 450 Meter
.
photo Suparni - Beritajakarta.id

Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. Takjil Supervision in Central Jakarta Begins Second Week

    access_time02-03-2025 remove_red_eye469 personBudhi Firmansyah Surapati
  2. Government Declares Ramadhan Starts on March 1, 2025

    access_time28-02-2025 remove_red_eye443 personBudhi Firmansyah Surapati
  3. Dishub: Lay Bay Remains Optimal to Support Public Transportation User Comfort

    access_time02-03-2025 remove_red_eye396 personAldi Geri Lumban Tobing
  4. Traffic Diverted on Jalan Jatinegara Barat as Floods Hit Jakarta

    access_time04-03-2025 remove_red_eye368 personNurito
  5. City Government Ensures Pondok Bambu Fire Survivors Needs are Met

    access_time01-03-2025 remove_red_eye331 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik