You don't have javascript enabled. Good luck with that.
Pencarian
Normalisasi Saluran Penghubung Malakasari Mencapai 450 Meter
.
photo Suparni - Beritajakarta.id

Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1210 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1053 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye907 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye735 personFolmer
  5. Jakarta Provincial Government Holds Christmas Carol

    access_time18-12-2024 remove_red_eye578 personDessy Suciati