Pembangunan Jalur Pedestrian di Daan Mogot Mencapai 54 Persen

Daan Mogot Pedestrian Arrangement Has Touched 54 Percent

We're optimistic that the project can finish on time

Progress of structuring the 1.7-kilometer length pedestrian track on Jalan Daan Mogot, West Jakarta, has so far reached 54 percent. It is expected that the project can be complete by the end of this year.

JPO's Iron Buffer on Jl. Daan Mogot Evacuated After Being Hit By Truck

West Jakarta Bina Marga Sub-dept. Head, Riswan Efendi said, his sub-dept. keeps optimizing the project.

"We're optimistic that the project can finish on time," he expressed, Friday (10/6).

He added the pedestrian would have park, bike track, disability steering tiles, park bench and good drainage.

"It's carried out along with related unit related to the main tasks and functions (tupoksi) For instance, park arrangement becomes the responsible of Forestry Sub-dept. and so on," he closed.

Linked News
Popular News indeks
  1. Pramono Flags Off 10,000 Runners at Soekarno Run 2026

    access_time15-02-2026 remove_red_eye1057 personFolmer
  2. Jakarta Unveils Indonesia’s First SDGs Corner at Maritime Museum

    access_time15-02-2026 remove_red_eye993 personNurito
  3. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye965 personAldi Geri Lumban Tobing
  4. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye925 personAldi Geri Lumban Tobing
  5. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye705 personAldi Geri Lumban Tobing
KONTAK KAMI
Berita Jakarta Berita Jakarta TV

Jl. Medan Merdeka Selatan 8-9 Blok F Lt. II Jakarta
local_phone +62 21 3822356
email redaksi@beritajakarta.id

TAUTAN LAINNYA
Tentang Kami | Sitemap | Infografis

© copyright 2001 - 2026 All Rights Reserved