Pramuka Island Plaza Pier Construction Has Touched 85 Percent
access_time November 03 2017 02:23 PM remove_red_eye 1227
Reported by Rudi Hermawan | Translated by Nugroho Adibrata
Reported by Rudi Hermawan | Translated by Nugroho Adibrata
The construction of Pramuka Island Plaza Pier, Panggang Island Urban Village, North Seribu Islands has reached 85 percent. It is targeted to be completed by the end of this month.
We spend Rp 4.5 billion to build the pier
"The project has reached 85 percent," said Suherman, Section Head of Facility and Infrastructure for Seribu Islands Transportation Sub-dept., Thursday (11/2).
He stated, thus far, it has entered stage of rubber installation on the side of the pier to hold the boat leaning. "Next is the installation of the archway and continued with arrangement of conblock," he expressed.
Liquor and Expired Food Confiscated from Pramuka IslandHe added the plaza pier design is altered extending from the UPAPK to the end of the RPTRA, shaped like V.
"We spend Rp 4.5 billion to build the pier," he closed.