Perbaikan Jalan di Kepulauan Seribu Selatan Sudah 40 Persen
.
photo istimewa - Beritajakarta.id

Road Repair Progress in Seribu Islands Reaches 40 Percent

Road repair is conducted in Untung Jawa, Tidung, and Lancang Islands. Its progress has reached 40 Percents and it is targeted to finish in December.

Several locations are in repairing progress. We target it to finish in December

South of Seribu Islands Sub-district Head, Agus Setiawan explained that three locations as long as 5,400 square meters will be repaired with total budget Rp 2,585 billion.

"Current progress reaches 40 percent," he said, Tuesday (11/28).

Road at Cilincing Bridge Needs Repair

He mentioned, con-block will be used for the repaired roads. Currently, personnel conducts concrete cansteen installation with sand in several locations.

"Several locations are in repairing progress. We target it to finish in December," he affirmed.   

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye954 personTP Moan Simanjuntak
  2. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye660 personBudhi Firmansyah Surapati
  3. Satpol PP Expels Illegal Participants at Sudirman - Thamrin CFD

    access_time27-10-2024 remove_red_eye454 personBudhi Firmansyah Surapati
  4. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye395 personTiyo Surya Sakti
  5. Traffic Arrangement Applied on Jalan Tambak

    access_time28-10-2024 remove_red_eye370 personAldi Geri Lumban Tobing