Sunter Lake Dam Targeted to Finish Two Weeks Ahead

North Jakarta Water Resources (SDA) Sub-dept. targets to complete dam construction on south side of Sunter Lake on February 20. For information, this work has been started since last week.

We start it from last week and target to complete it on February 20

North Jakarta SDA Sub-dept. Head, Santo conveyed, his side constructs dam along 90 meters on west side of lake.

Sunter Lake Arrangement Reaches 30 Percent

"We start it from last week and target to complete it on February 20," he affirmed, Wednesday (2/7).

Not only to prevent landslide, but this dam with around 2.5 meters wide is also prepared to support tourism.

"We use river stone for its material. We give sloof in each 20 meters for citizen who wants to sit or for fishing spot," he explained.

Linked News
Popular News indeks
  1. City Council Strengthens Synergy with Central Legislators to Support Jakarta`s Development

    access_time30-07-2026 remove_red_eye1100 personFakhrizal Fakhri
  2. Jakarta Partners with Five Satellite Cities for Greater Jakarta Connected Initiative

    access_time30-07-2026 remove_red_eye638 personBudhi Firmansyah Surapati
  3. Still Rp 3,500! No Fare Change for Transjakarta’s Kalideres–Soetta Route

    access_time01-08-2026 remove_red_eye546 personAldi Geri Lumban Tobing
  4. Jakarta Reaffirms Commitment to Preserving Cultural Heritage

    access_time31-07-2026 remove_red_eye523 personDessy Suciati
  5. New LapakMain Corner Creative Hub Inaugurated at Tunas Muda RPTRA, Kramat Pela

    access_time05-08-2026 remove_red_eye511 personTiyo Surya Sakti