250 Joint PHL Personnel Deployed to Arrange Sunter Lake Sidewalk
Reported by Budhi Firmansyah Surapati | Translated by Maria Inggita
North Jakarta Administration deployed 250 PHL from Bina Marga Sub-dept., Environment (LH) Sub-dept., Water Resources (SDA) Sub-dept., Forestry Sub-dept., and PPSU to accelerate Sunter Lake arrangement progress.
There are 250 joint personnel from Bina Marga, LH, SDA, Forestry, and PPSU. Each urban villages send us four personnel
North Jakarta Mayor, Husein Murad mentioned, his side deployed hundreds personnel to install paving blocks for around 100 meters long sidewalk since it is targeted to finish this week.
Sunter Lake Conceptualized Into Integrated Water Tourism Area"There are 250 joint personnel from Bina Marga, LH, SDA, Forestry, and PPSU. Each urban villages send us four personnel," he informed, Monday (2/12).
He explained, personnel is divided in two shifts. First shift works from 8 AM to 3 PM and next shift is from 3 to 8 PM.
"Currently its progress reaches around 60 percent. We could be more focused for the event in the last week if sidewalk could be done this week," he stated.