Pembangunan LRT Sudah Capai 65,17 Persen
.
photo Wuri Setyaningsih - Beritajakarta.id

LRT Construction Has Reached 65.17 Percent

PT. Jakpro President Director, Satya Heragandhi disclosed, the Light Rail Transit (LRT) construction in the capital has reached 65.17 percent.

The construction of the first phase corridor as long as 5.8 kilometers and other depots is targeted to be completed prior to the 2018 Asian Games

The development progress includes the construction of the P102 package project or the main construction package that reaches 65%. Further, the work of P103 package in the form of train procurement that reaches 61% and operational planning (Operational Plan) has reached 45%.

Jakpro Optimists to Test LRT on Schedule

"The construction of the first phase corridor as long as 5.8 kilometers and other depots is targeted to be completed prior to the 2018 Asian Games," he expressed, Friday (3/30).

He explained, LRT Jakarta has 6 stations, namely Depot Station, Kelapa Gading Mall, Kelapa Gading Boulevard, Pulomas, Pacuan Kuda, and Velodrome. 

"Eventually those stations will be connected with venue locations, Transjakarta bus lanes and east-west MRT station," he stated.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1505 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye928 personAldi Geri Lumban Tobing
  3. Gulkarmat to Intensify Fire Mitigation Education

    access_time22-01-2025 remove_red_eye407 personBudhi Firmansyah Surapati
  4. BMKG Warns of Potential High Rainfall in Jakarta

    access_time22-01-2025 remove_red_eye401 personDessy Suciati
  5. City and Kejati Forge Cooperation for Good Government Governance

    access_time21-01-2025 remove_red_eye395 personFolmer