Pembangunan LRT Sudah Capai 65,17 Persen
.
photo Wuri Setyaningsih - Beritajakarta.id

LRT Construction Has Reached 65.17 Percent

PT. Jakpro President Director, Satya Heragandhi disclosed, the Light Rail Transit (LRT) construction in the capital has reached 65.17 percent.

The construction of the first phase corridor as long as 5.8 kilometers and other depots is targeted to be completed prior to the 2018 Asian Games

The development progress includes the construction of the P102 package project or the main construction package that reaches 65%. Further, the work of P103 package in the form of train procurement that reaches 61% and operational planning (Operational Plan) has reached 45%.

Jakpro Optimists to Test LRT on Schedule

"The construction of the first phase corridor as long as 5.8 kilometers and other depots is targeted to be completed prior to the 2018 Asian Games," he expressed, Friday (3/30).

He explained, LRT Jakarta has 6 stations, namely Depot Station, Kelapa Gading Mall, Kelapa Gading Boulevard, Pulomas, Pacuan Kuda, and Velodrome. 

"Eventually those stations will be connected with venue locations, Transjakarta bus lanes and east-west MRT station," he stated.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1036 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye902 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye541 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye446 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye379 personAldi Geri Lumban Tobing