Pembangunan LRT Sudah Capai 65,17 Persen
.
photo Wuri Setyaningsih - Beritajakarta.id

LRT Construction Has Reached 65.17 Percent

PT. Jakpro President Director, Satya Heragandhi disclosed, the Light Rail Transit (LRT) construction in the capital has reached 65.17 percent.

The construction of the first phase corridor as long as 5.8 kilometers and other depots is targeted to be completed prior to the 2018 Asian Games

The development progress includes the construction of the P102 package project or the main construction package that reaches 65%. Further, the work of P103 package in the form of train procurement that reaches 61% and operational planning (Operational Plan) has reached 45%.

Jakpro Optimists to Test LRT on Schedule

"The construction of the first phase corridor as long as 5.8 kilometers and other depots is targeted to be completed prior to the 2018 Asian Games," he expressed, Friday (3/30).

He explained, LRT Jakarta has 6 stations, namely Depot Station, Kelapa Gading Mall, Kelapa Gading Boulevard, Pulomas, Pacuan Kuda, and Velodrome. 

"Eventually those stations will be connected with venue locations, Transjakarta bus lanes and east-west MRT station," he stated.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1207 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1052 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye903 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye729 personFolmer
  5. Jakarta Provincial Government Holds Christmas Carol

    access_time18-12-2024 remove_red_eye574 personDessy Suciati