Three Connecting Channels in C. Jakarta Normalized
access_time May 31 2018 02:31 PM remove_red_eye 1188
Reported by Suparni | Translated by Nugroho Adibrata
Reported by Suparni | Translated by Nugroho Adibrata
Three connecting channels in some areas, Central Jakarta began to be normalized. Besides that, some damaged sheet piles are also repaired to hinder landslide.
Its project includes sediment dredging, sheet pile repair and manhole cover repair without changing the height and channel to anticipate puddle
Central Jakarta Water Resources Sub-dept. Head, Dicky Suherlan stated his side is currently accelerating the project.
"Its project includes sediment dredging, sheet pile repair and manhole cover repair without changing the height and channel to anticipate puddle," he expressed, Thursday (5/31).
Channels of Jalan Nyiur Raya NormalizedThose channels are Tanah Tinggi XII channel (200 meters length), Sukarjo channel until Harmoni (500 meters length), and Bendungan Hilir Raya channel (500 meters length).
"Every day, we send 10-12 officers to the field. Hopefully it can be finished by the end of June," he stated.