Docking Groove Construction in Kelapa Island Targeted to Complete by December

Docking groove on the northern side of Kelapa Island Pier will be built and upgraded soon. It is targeted to complete by the end of December 2018.

Its budget is about Rp 8.6 billion and we plan to complete it in four months

Seribu Islands Transportation Sub-dept.'s Facility and Infrastructure Section Head, Suherman mentioned, his side starts to remeasure the site and ensure several works needed to be done in this project.

"Today we repeat the measurement for docking groove deepening. Later on, we will start the work," he said, Wednesdy (8/29).

Cilincing Floating Dock Construction Completed

He added, this construction is one of resident's requests in Musrenbang (development planning discussion).

"Its budget is about Rp 8.6 billion and we plan to complete it in four months," he informed.

Linked News
Popular News indeks
  1. Kampung Melayu Sports Facility Inaugurated to Tackle Brawls

    access_time06-11-2026 remove_red_eye550 personDessy Suciati
  2. Aid for Fire Survivors at Pinus Elok Flats Has Been Distributed

    access_time06-11-2026 remove_red_eye535 personNurito
  3. Jakarta to Develop Its First Mangrove Botanical Garden

    access_time06-11-2026 remove_red_eye511 personDessy Suciati
  4. Commission D Calls for Integrated Air Quality Monitoring System

    access_time06-11-2026 remove_red_eye502 personFakhrizal Fakhri
  5. Kampung Rambutan 1 Reservoir to Combine Flood Control with Public Recreation

    access_time06-11-2026 remove_red_eye498 personAldi Geri Lumban Tobing