 Pembangunan Kolam Labuh di Pulau Kelapa Ditarget Rampung Desember

Docking Groove Construction in Kelapa Island Targeted to Complete by December

Docking groove on the northern side of Kelapa Island Pier will be built and upgraded soon. It is targeted to complete by the end of December 2018.

Its budget is about Rp 8.6 billion and we plan to complete it in four months

Seribu Islands Transportation Sub-dept.'s Facility and Infrastructure Section Head, Suherman mentioned, his side starts to remeasure the site and ensure several works needed to be done in this project.

"Today we repeat the measurement for docking groove deepening. Later on, we will start the work," he said, Wednesdy (8/29).

Cilincing Floating Dock Construction Completed

He added, this construction is one of resident's requests in Musrenbang (development planning discussion).

"Its budget is about Rp 8.6 billion and we plan to complete it in four months," he informed.

Linked News
Popular News indeks
  1. Nighttime Surveillance on Railroad Banks of Jalan I Gusti Ngurah Rai Intensified

    access_time08-05-2026 remove_red_eye2617 personNurito
  2. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye953 personFolmer
  3. PSEL Project to Solve Jakarta's Waste Crisis, Says Pramono

    access_time06-05-2026 remove_red_eye911 personDessy Suciati
  4. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye807 personFakhrizal Fakhri
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye715 personBudhi Firmansyah Surapati