Seven Roads in Kramat Jati Concreted
Reported by Nurito | Translated by Nugroho Adibrata
The concretization process at seven road points in Kramat Jati Sub-district, East Jakarta has now been completed. The rest is targeted for completion in the upcoming October.
From eight points in Kramat Jati, seven out of them have been completed
East Jakarta Bina Marga Sub-dept.'s Maintenance Section Head, Benediktus Situmorang stated that it has been conducted since June 2018. And now his side focuses on completion of concretization along Jalan Raya Kober, in Kampung Tengah Urban Village, along 252 meters.
Concretization Process at Jalan Pejagalan Has Touched 60 Percent"From eight points in Kramat Jati, seven out of them have been completed. The rest is at Jalan Raya Kober that is still ongoing," he stated, Tuesday (9/4).
According to him, seven concretization work points that have been completed, namely repair of Jalan Generasi as long as 420.7 meters with three meters width.
There are also Jalan Remaja II as long as 281 meters, Jalan Rantai Perak as long as 76 meters, Jalan TPS as long as 85 meters, Jalan Jalan H. Tabri Batu Ampar as long as 84 meters, Jalan Pulo Dukuh as long as 92 meters, and Jalan Penggilingan Baru Kelurahan Dukuh as long as 45 meters.