IPAL Constructed in Lancang Island
access_time September 14 2018 04:14 PM remove_red_eye 1520
Reported by Rudi Hermawan | Translated by Maria Inggita
Reported by Rudi Hermawan | Translated by Maria Inggita
Seribu Islands Water Resources (SDA) Sub-dept. constructs Wastewater Treatment Installation (IPAL) in Lancang Island. This project is targeted to finish in December 2018.
IPAL will be connected to 600 houses in Lancang Island
"We have started this construction in August. Our target is to complete it on December 15," informed Ahmad Saiful, Seribu Islands SDA Sub-dept., Friday (9/14).
PD. PAL Jaya-Lions Club Established Cooperation Related to Sanitation ManagementIPAL will be constructed in two zoning areas. Zone 1 is made for 250 houses and zone 2 for 350 houses.
"IPAL will be connected to 600 houses in Lancang Island. Its budget i
s Rp 9.9 billion," he stated.