Progres Pembangunan Tanggul NCICD di Marunda Capai 63 Persen

Dike Construction for NCICD Project in Marunda Reaches 63 Percent

Construction on Dike A as a part of National Capital Integrated Coastal Development (NCICD)'s project in Blencong River estuary, Marunda Urban Village, Cilincing, North Jakarta is now reached 63 percent from total target 1,019 meters long.

We target to install 1,056 spun piles along 1,019 meters in total

Jakarta Water Resources (SDA) Dept.'s Development River Improvement and East Flow Coastal System Section Head, Andika Purnomo mentioned, currently 555 spun piles have been installed along 527 meters.

NCICD Giant Sea Wall Phase A Project in Marunda Resumed

"We target to install 1,056 spun piles along 1,019 meters in total. Currently, we have installed around 63 percent and there are still 501 remaining piles," he informed, Wednesday (10/23).

He explained, it is done as the continuation of the work in 2016 and 2017. In 2016, a 256-meter dike was built, and it continued to 368 meters in 2017.

"This year's construction is targeted to be done in December. We will continue it in 2019 and we will start to build jalan inspeksi (waterfront) in 2020-2022," he stated.

Linked News
Popular News indeks
  1. City Council Strengthens Synergy with Central Legislators to Support Jakarta`s Development

    access_time30-07-2026 remove_red_eye1076 personFakhrizal Fakhri
  2. Jakarta Partners with Five Satellite Cities for Greater Jakarta Connected Initiative

    access_time30-07-2026 remove_red_eye602 personBudhi Firmansyah Surapati
  3. Pramono Praises Young Innovators at the Jakarta Robotic Games 2026

    access_time28-07-2026 remove_red_eye488 personDessy Suciati
  4. Jakarta Reaffirms Commitment to Preserving Cultural Heritage

    access_time31-07-2026 remove_red_eye486 personDessy Suciati
  5. Various Events Prepared for Jakarta`s 5th Century Anniversary

    access_time29-07-2026 remove_red_eye472 personFakhrizal Fakhri