Progres Pembangunan Tanggul NCICD di Marunda Capai 63 Persen

Dike Construction for NCICD Project in Marunda Reaches 63 Percent

Construction on Dike A as a part of National Capital Integrated Coastal Development (NCICD)'s project in Blencong River estuary, Marunda Urban Village, Cilincing, North Jakarta is now reached 63 percent from total target 1,019 meters long.

We target to install 1,056 spun piles along 1,019 meters in total

Jakarta Water Resources (SDA) Dept.'s Development River Improvement and East Flow Coastal System Section Head, Andika Purnomo mentioned, currently 555 spun piles have been installed along 527 meters.

NCICD Giant Sea Wall Phase A Project in Marunda Resumed

"We target to install 1,056 spun piles along 1,019 meters in total. Currently, we have installed around 63 percent and there are still 501 remaining piles," he informed, Wednesday (10/23).

He explained, it is done as the continuation of the work in 2016 and 2017. In 2016, a 256-meter dike was built, and it continued to 368 meters in 2017.

"This year's construction is targeted to be done in December. We will continue it in 2019 and we will start to build jalan inspeksi (waterfront) in 2020-2022," he stated.

Linked News
Popular News indeks
  1. The Lights-Out Action Successfully Reduces Carbon Emissions

    access_time27-04-2026 remove_red_eye549 personAldi Geri Lumban Tobing
  2. MRT Jakarta Urged to Enhance Power Outage Mitigation System

    access_time27-04-2026 remove_red_eye540 personFakhrizal Fakhri
  3. Dharma Jaya Sets Strategy to Bolster Jakarta Food Security

    access_time27-04-2026 remove_red_eye448 personAldi Geri Lumban Tobing
  4. Rano Pays Condolence Visit to Bekasi Train Crash Victim in Kemayoran

    access_time29-04-2026 remove_red_eye443 personBudhi Firmansyah Surapati
  5. 70 Kayu Manis Residents Trained in Waste Sorting

    access_time25-04-2026 remove_red_eye442 personNurito