Progres Pembangunan Tanggul NCICD di Marunda Capai 63 Persen

Dike Construction for NCICD Project in Marunda Reaches 63 Percent

Construction on Dike A as a part of National Capital Integrated Coastal Development (NCICD)'s project in Blencong River estuary, Marunda Urban Village, Cilincing, North Jakarta is now reached 63 percent from total target 1,019 meters long.

We target to install 1,056 spun piles along 1,019 meters in total

Jakarta Water Resources (SDA) Dept.'s Development River Improvement and East Flow Coastal System Section Head, Andika Purnomo mentioned, currently 555 spun piles have been installed along 527 meters.

NCICD Giant Sea Wall Phase A Project in Marunda Resumed

"We target to install 1,056 spun piles along 1,019 meters in total. Currently, we have installed around 63 percent and there are still 501 remaining piles," he informed, Wednesday (10/23).

He explained, it is done as the continuation of the work in 2016 and 2017. In 2016, a 256-meter dike was built, and it continued to 368 meters in 2017.

"This year's construction is targeted to be done in December. We will continue it in 2019 and we will start to build jalan inspeksi (waterfront) in 2020-2022," he stated.

Linked News
Popular News indeks
  1. Pramono Pushes to Complete Long-Delayed Pluit JLNT by March 2027

    access_time20-11-2026 remove_red_eye701 personDessy Suciati
  2. JAF 2026 Highlights Maritime Heritage and Coastal Architecture

    access_time21-11-2026 remove_red_eye689 personAnita Karyati
  3. Hosted in Sydney, Pramono Discusses Opening Australian Campuses in Jakarta

    access_time25-11-2026 remove_red_eye678 personDessy Suciati
  4. Jakarta Strengthens ASEAN Cooperation on Climate, Transport, and Youth

    access_time20-11-2026 remove_red_eye639 personFolmer
  5. BORJU Markets 200 Local Products

    access_time20-11-2026 remove_red_eye607 personAnita Karyati