Progres Pembangunan Tanggul NCICD di Marunda Capai 63 Persen
.
photo Budhi Firmansyah Surapati - Beritajakarta.id

Dike Construction for NCICD Project in Marunda Reaches 63 Percent

Construction on Dike A as a part of National Capital Integrated Coastal Development (NCICD)'s project in Blencong River estuary, Marunda Urban Village, Cilincing, North Jakarta is now reached 63 percent from total target 1,019 meters long.

We target to install 1,056 spun piles along 1,019 meters in total

Jakarta Water Resources (SDA) Dept.'s Development River Improvement and East Flow Coastal System Section Head, Andika Purnomo mentioned, currently 555 spun piles have been installed along 527 meters.

NCICD Giant Sea Wall Phase A Project in Marunda Resumed

"We target to install 1,056 spun piles along 1,019 meters in total. Currently, we have installed around 63 percent and there are still 501 remaining piles," he informed, Wednesday (10/23).

He explained, it is done as the continuation of the work in 2016 and 2017. In 2016, a 256-meter dike was built, and it continued to 368 meters in 2017.

"This year's construction is targeted to be done in December. We will continue it in 2019 and we will start to build jalan inspeksi (waterfront) in 2020-2022," he stated.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1036 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye902 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye544 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye446 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye379 personAldi Geri Lumban Tobing