 Pengerjaan Pengerukan Waduk Pluit Capai 30 Persen
.
photo Budhi Firmansyah Surapati - Beritajakarta.id

Pluit Reservoir Dredging Has Reached 30 Percent

Its dredging is done up to 80 hectares which aims to accommodate water in large quantities

The Pluit Reservoir dredging process that has been carried out since April has reached 30 percent 

Commission D Appreciates Mud Dredging Work at Pluit Reservoir

Jakarta Water Resources Agency's Operation and Flow System Maintenance Division Head, Firmansyah Saputra said that some reservoir areas are still full of mud with varying heights. 

"Its dredging is done up to 80 hectares which aims to accommodate water in large quantities," he expressed, Tuesday (8/13).

To conduct it, as many as 18 excavators and 40 officers have been sent to deepen reservoir between one to two meters from the LWL (Low Water Fussy).

It is hoped able to minimize inundation in Pluit, Ancol, Kota, Pasar Baru and Monas areas when it rains.

"It is targeted to be finished by the end of November," he stated. 

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye950 personTP Moan Simanjuntak
  2. Second Pilkada 2024 Debate Theme Set, Don't Miss It

    access_time26-10-2024 remove_red_eye777 personAldi Geri Lumban Tobing
  3. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye643 personBudhi Firmansyah Surapati
  4. Satpol PP Expels Illegal Participants at Sudirman - Thamrin CFD

    access_time27-10-2024 remove_red_eye454 personBudhi Firmansyah Surapati
  5. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye392 personTiyo Surya Sakti