Pembangunan Sebelas Saluran Air Baru di Jaktim Capai 50 Persen

11 New Channels Construction in East Jakarta Reaches 50 Percent

East Jakarta Water Resources Sub-department is currently building 11 new water channel in East Jakarta. It is built to realize resident's request through Planning and Development Discussion (Musrenbang) 2018.

Our target is to compete it in December 2019

"In average, new water channels construction process has reached 50 percent. These channels are made to anticipate inundation and flood in rainy season," stated Santo, East Jakarta Water Resources Sub-department Head, Friday (9/13).

First channel is located on Jalan Mini I and III Bambu Apus installed with 60x60 cm and 80x80 cm U-ditch concrete as long as 1,357 meters. Then, on Jalan Pondok Bambu with length 509 meters installed with 80x80 cm U-ditch concrete, on Jalan Cipinang Cempedak IV with length 312 meters installed with 60x80 cm U-ditch concrete.

Channel Draining in 56 Urban Villages must Be Accelerated

Then channel on Jl. Tipar Cakung as long as 1,081 meters installed with 100x100 cm and 80x80 cm U-ditch concrete, channel on Griya Tipar Cakung Public Housing (Rusun) as long as 757 cm using 100x100 and 150x150 cm U-ditch concrete.

Next, channel on Jl. Cipinang Kebembem until Jl. Bekasi Raya, Pulogadung with length 602 meters using 100x100 cm and 120x120 cm U-ditch concrete, channel on Jl. Bulak Ringin, Cibubur as long as 648 meters using 40x40 cm and 80x80 cm U-ditch concrete, channel on Jl. A-Syafiiyah Cilangkap with length 1,143 square meters using 80x80 cm and 60x60 cm U-ditch concrete.

Next, channel on Jl. Raya Pondok Ranggon with length 650 meters using 60x60 cm and 80x80 cm U-ditch concrete, channel on Jl. Kandang Sapi cakung Timur as long as 478 meters using 100x100 cm U-ditch concrete.

"Last, channel on Jalan Pangeran Jayakarta until Jalan Bekasi Timur as long as 1,049 square meters using 100x100 cm and 120x120 cm box culvert," he informed.

According to him, his side uses U-ditch and box culvert concrete to build those channels since its material is stronger to prevent landslide.

"This construction uses Rp 21.8 billion taken from City Budget (APBD) 2019. Our target is to compete it in December 2019," he mentioned.

Linked News
Popular News indeks
  1. Volcanic Ash Reaches Jakarta, Health Agency Calls for Protective Measures

    access_time06-09-2026 remove_red_eye1652 personBudhi Firmansyah Surapati
  2. BMKG: Sunny to Cloudy Skies Forecast Across Jakarta Today

    access_time11-09-2026 remove_red_eye1504 personDessy Suciati
  3. Jakartans Urged to Stay Calm and Take Precautions Amid Mt. Anak Krakatau Volcanic Ash

    access_time06-09-2026 remove_red_eye834 personBudhi Firmansyah Surapati
  4. Jakarta Provincial Government Anticipates the Impact of Volcanic Ash from Mount Anak Krakatau

    access_time06-09-2026 remove_red_eye689 personFolmer
  5. Jakarta Reallocates Funds for Rp 250M Suckermouth Catfish Study After Pramono’s Direct Order

    access_time10-09-2026 remove_red_eye654 personFakhrizal Fakhri