Until December, Bina Marga Targeted to Concrete 107 Collector Roads in North Jakarta

North Jakarta Bina Marga Sub-department concretes 107 collector roads in six urban villages. This project is started in September and targeted to finish in December.

It is to follow up residents proposal on Musrenbang 2018

North Jakarta Bina Marga Sub-department's Bridge and Road Maintenance Section Head, Ujang Royani stated, each collector roads have different width and length. Those roads will be concreted with thickness around 25 centimeters.

"It is to follow up residents proposal on Musrenbang 2018. They asked to elevate the road because its condition is damaged and often submerged in puddles," he explained, Monday (9/30).

Sidewalk Improvement in Tanah Abang Finished

In detail, he continued, there are 15 collector roads in Penjaringan, 13 collector roads in Pademangan, 40 collector roads in Tanjung Priok, 14 collector roads in Koja, 10 collector roads in Kelapa Gading, and 15 collector roads in Cilincing Sub-districts.

According to him, this project is involving assistance and monitoring from North Jakarta District Prosecutor's Security Team for Government and Regional Development (TP4D), starts from its planning stage until finish.

"Total area that need to be concreted reaches around 161,474 square meters. Our target is to complete it in mid of this December," he conveyed.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1681 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1470 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1331 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1111 personDessy Suciati
  5. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye797 personDessy Suciati