 Pengerjaan Turap di Kali Sentiong Kelurahan Paseban Mencapai 30 Persen

Sheet Pile Installation on Sentiong River Has Reached 23 Percent

The sheet pile installation progress on the Sentiong River, Paseban Urban Village, Senen, Central Jakarta has reached 23 percent. 

To do it, we have deployed 20 personnel to the location

Senen Sub-district Water Resources Executing Unit Head Rohman said it is carried out to strengthen the river wall structures in order to anticipate landslides.

Karang Bolong River Uses Old Tires as Sheet Pile Naturalization

"Its installation is carried out up to 310 meters and has been done about 70 meters," he expressed, Monday (9/30).

This work that has been ongoing since September 2 is targeted to be complete on October 27.

"To do it, we have deployed 20 personnel to the location," he stated.

As for the information, the sheet pile will have 2 meters height with a foundation of 60 centimeters width.

Linked News
Popular News indeks
  1. 21 Parking Spots to Make Your Jakarta 499th Anniversary Experience Seamless

    access_time26-06-2026 remove_red_eye894 personAldi Geri Lumban Tobing
  2. Over 11 Kilometers of Overhead Utility Cables Removed in West Jakarta

    access_time26-06-2026 remove_red_eye868 personBudhi Firmansyah Surapati
  3. Celebrating Jakarta`s 499th Anniversary at HI, Please Use Public Transportation

    access_time26-06-2026 remove_red_eye734 personAldi Geri Lumban Tobing
  4. 190 Satpol PP Personnel Deployed to Secure Jakarta Anniversary Celebration

    access_time26-06-2026 remove_red_eye693 personFolmer
  5. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye665 personDessy Suciati