 Pengerjaan Turap di Kali Sentiong Kelurahan Paseban Mencapai 30 Persen
.
photo Agung Supriyanto - Beritajakarta.id

Sheet Pile Installation on Sentiong River Has Reached 23 Percent

The sheet pile installation progress on the Sentiong River, Paseban Urban Village, Senen, Central Jakarta has reached 23 percent. 

To do it, we have deployed 20 personnel to the location

Senen Sub-district Water Resources Executing Unit Head Rohman said it is carried out to strengthen the river wall structures in order to anticipate landslides.

Karang Bolong River Uses Old Tires as Sheet Pile Naturalization

"Its installation is carried out up to 310 meters and has been done about 70 meters," he expressed, Monday (9/30).

This work that has been ongoing since September 2 is targeted to be complete on October 27.

"To do it, we have deployed 20 personnel to the location," he stated.

As for the information, the sheet pile will have 2 meters height with a foundation of 60 centimeters width.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1507 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye929 personAldi Geri Lumban Tobing
  3. Gulkarmat to Intensify Fire Mitigation Education

    access_time22-01-2025 remove_red_eye431 personBudhi Firmansyah Surapati
  4. BMKG Warns of Potential High Rainfall in Jakarta

    access_time22-01-2025 remove_red_eye411 personDessy Suciati
  5. City and Kejati Forge Cooperation for Good Government Governance

    access_time21-01-2025 remove_red_eye399 personFolmer