 Pengerjaan Turap di Kali Sentiong Kelurahan Paseban Mencapai 30 Persen
.
photo Agung Supriyanto - Beritajakarta.id

Sheet Pile Installation on Sentiong River Has Reached 23 Percent

The sheet pile installation progress on the Sentiong River, Paseban Urban Village, Senen, Central Jakarta has reached 23 percent. 

To do it, we have deployed 20 personnel to the location

Senen Sub-district Water Resources Executing Unit Head Rohman said it is carried out to strengthen the river wall structures in order to anticipate landslides.

Karang Bolong River Uses Old Tires as Sheet Pile Naturalization

"Its installation is carried out up to 310 meters and has been done about 70 meters," he expressed, Monday (9/30).

This work that has been ongoing since September 2 is targeted to be complete on October 27.

"To do it, we have deployed 20 personnel to the location," he stated.

As for the information, the sheet pile will have 2 meters height with a foundation of 60 centimeters width.

Linked News
Popular News indeks
  1. Five Transjabodetabek Routes will Be Added to Tackle Traffic Congestion

    access_time09-05-2025 remove_red_eye668 personDessy Suciati
  2. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye459 personFolmer
  3. Munjirin Optimizes Physical and Non-Physical Development in East Jakarta

    access_time08-05-2025 remove_red_eye377 personNurito
  4. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye355 personFolmer
  5. Baduy Tribe Meets Pramono-Rano, Leaves Message of Protecting Nature

    access_time09-05-2025 remove_red_eye295 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik