Normalisasi Saluran Jl Puskesmas Kelapa Gading Timur Capai 98 Persen

Channel Normalization on Jalan Puskesmas Has Reached 98 Percent

The work has touched 98 percent and is targeted to be complete in the next few days

The water channel normalization on Jalan Puskesmas, RW 06, Kelapa Gading Timur Urban Village, North Jakarta has entered final stage.

Kelapa Gading Sub-district Water Resources Executing Unit Head Rukmana said this project leaves the completion of the installation of concrete manhole covers.

Channel on Jalan Kalibata Utara II Normalized

"The work progress has touched 98 percent and is targeted to be complete in the next few days," he expressed, Monday (10/7).

She explained normalization is done as the channel condition is damaged severely and some of the material collapses until it blocks the water flow.

"This repair was proposed by residents through the 2019 Musrenbang," he stated.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye870 personTiyo Surya Sakti
  2. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye657 personTiyo Surya Sakti
  3. Pramono: Jakarta Government Acts Swiftly to Tackle Flooding

    access_time30-01-2026 remove_red_eye369 personDessy Suciati
  4. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye369 personAldi Geri Lumban Tobing
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye362 personDessy Suciati
close