You don't have javascript enabled. Good luck with that.
Pencarian
Normalisasi Saluran Jl Puskesmas Kelapa Gading Timur Capai 98 Persen

Channel Normalization on Jalan Puskesmas Has Reached 98 Percent

The work has touched 98 percent and is targeted to be complete in the next few days

The water channel normalization on Jalan Puskesmas, RW 06, Kelapa Gading Timur Urban Village, North Jakarta has entered final stage.

Kelapa Gading Sub-district Water Resources Executing Unit Head Rukmana said this project leaves the completion of the installation of concrete manhole covers.

Channel on Jalan Kalibata Utara II Normalized

"The work progress has touched 98 percent and is targeted to be complete in the next few days," he expressed, Monday (10/7).

She explained normalization is done as the channel condition is damaged severely and some of the material collapses until it blocks the water flow.

"This repair was proposed by residents through the 2019 Musrenbang," he stated.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye428 personFakhrizal Fakhri
  3. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye394 personTiyo Surya Sakti
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye359 personDessy Suciati
close