 Pengerjaan Normalisasi Saluran Di Jalan Kartini 8A Capai 98 Persen

Channel Normalization on Jalan Kartini 8A Reaches 98 Percent

Its normalization is done up to 90 meters length

The water channel normalization work on Jalan Kartini 8A, Kartini Urban Village, Sawah Besar Sub-district, Central Jakarta has reached 98 percent.

"Its normalization is done up to 90 meters length," said Sawah Besar Sub-district Water Resources Executing Unit Head, Nanang Gusnadi, Friday (11/29).

Kramat Jati Villagers Want Channels Normalization to Be a Priority

The work that has been ongoing since November 18 has a purpose for dredging mud and waste, as well as installing a U-ditch measuring 60x60x120 centimeters.

"To dredge them, we use one unit of excavator plus ten officers," he told.

It is targeted to be finished on November 30. "Right now is entering the finishing stage and will be complete tomorrow," he closed.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye428 personFakhrizal Fakhri
  3. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye416 personTiyo Surya Sakti
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye359 personDessy Suciati
close