Channel Normalization on Jalan Kartini 8A Reaches 98 Percent
access_time November 29 2019 04:58 PM remove_red_eye 1274
Reported by Agung Supriyanto | Translated by Nugroho Adibrata
Reported by Agung Supriyanto | Translated by Nugroho Adibrata
Its normalization is done up to 90 meters length
The water channel normalization work on Jalan Kartini 8A, Kartini Urban Village, Sawah Besar Sub-district, Central Jakarta has reached 98 percent.
"Its normalization is done up to 90 meters length," said Sawah Besar Sub-district Water Resources Executing Unit Head, Nanang Gusnadi, Friday (11/29).
Kramat Jati Villagers Want Channels Normalization to Be a PriorityThe work that has been ongoing since November 18 has a purpose for dredging mud and waste, as well as installing a U-ditch measuring 60x60x120 centimeters.
"To dredge them, we use one unit of excavator plus ten officers," he told.
It is targeted to be finished on November 30. "Right now is entering the finishing stage and will be complete tomorrow,"
he closed.