Pelebaran Jembatan Kali Caglak Capai 75 persen

Kali Caglak Bridge Widening Process Already 75 Percent

The Kali Caglak Bridge widening progress located at Jalan Lapangan Tembak, Cibubur, East Jakarta has reached 75 percent. The work that spent by Rp 1 billion will finish in mid-December.

After the fence is done, we will focus on the installation of wing railings

East Jakarta Bina Marga Sub-department's Road and Bridge Division Head Benediktus Situmorang said this widening work keeps being accelerated. After installing a voide sloop, it will be continued with the installation of a safety fence on the left side of the bridge and is targeted to be completed tonight.

"After the fence is done, we will focus on the installation of wing railings," he expressed, Wednesday (12/4).

Caglak River Bridge Widening Project Targeted to Finish in December

It is done on the left and right sides of the bridge with 12 meters long and 2 meters wide. If it is done, the bridge would have 6 meters long become 10 meters.

Linked News
Popular News indeks
  1. China-Based Training Equips PR Professionals and Journalists for Digital Media Transformation

    access_time19-07-2026 remove_red_eye1559 personFakhrizal Fakhri
  2. Jakarta Supports Social Media Restrictions for Children

    access_time20-07-2026 remove_red_eye1171 personFakhrizal Fakhri
  3. Commission E Enlists Religious Leaders to Fight Drugs and Violence

    access_time24-07-2026 remove_red_eye1158 personFakhrizal Fakhri
  4. Fire at Spark Sport Academy Pondok Bambu Successfully Extinguished

    access_time20-07-2026 remove_red_eye1002 personNurito
  5. Pramono and Coop Minister Kick Off Gen Coop Run 5K

    access_time19-07-2026 remove_red_eye800 personFakhrizal Fakhri