Seawall Construction on Karya Island Has Touched 90 Percent

We have sent eight workers to finish it

The construction of a seawall (called outer sea dike) on the north and east sides of Karya Island, Panggang Island Urban Village has touched more than 90 percent and is targeted to be complete by the end of this month.

"We have sent eight workers to finish it," expressed Thousand Islands Water Resources Sub-agency Head, Abdul Rauf, Tuesday (3/24).

This Week, Elevation of Rawa Badak Utara River’s Dike Finished

Specifically for the north side, the seawall is made up to 55 meters long with 1.30 meters wide and 80 centimeters high. While the east side has 57.80 meters long with 1.30 meters wide and 80 centimeters high.

"We make it to reduce land subsidence on Karya Island due to waves," he hoped.

Linked News
Popular News indeks
  1. Transjakarta Resumes Operations with Strategic Service Adjustments

    access_time28-08-2026 remove_red_eye909 personAldi Geri Lumban Tobing
  2. Jakarta Deploys 120 Personnel to Counteract Traffic Disruption for Today’s Protests

    access_time27-08-2026 remove_red_eye807 personAldi Geri Lumban Tobing
  3. JIF Summit 2026 Drives Global Partnerships and Investment Growth in Jakarta

    access_time28-08-2026 remove_red_eye641 personAldi Geri Lumban Tobing
  4. Transjakarta Commits to Accelerating Modal Integration and Fleet Electrification

    access_time31-08-2026 remove_red_eye473 personAldi Geri Lumban Tobing
  5. Drainage Normalization on Jalan Mandioli to Be Completed in October

    access_time28-08-2026 remove_red_eye470 personFolmer