Jakarta Transportation Agency (Dishub) implements traffic engineering on Jalan MH. Thamrin, Central Jakarta, due to Mass Rapid Transit (MRT) Phase II construction.

For the first stage of construction work on Jalan MH. Thamrin will be started from Bundaran HI MRT Station until National Monument (Monas)'s Fountain Roundabout

Through MRT Phase II construction project, MRT will expand and connect its lane from Bundaran HI MRT Station to Kota Tua which divided into 3 sections; CP 201, CP 202, and CP 203.

Jakarta Dishub Head, Syafrin Liputo conveyed, the construction will be started from Bundaran HI Station to Simpang Harmoni which called the CP 201 section.

MRT Phase II Construction will Be Postponed Until June 2020

"For the first stage of construction work on Jalan MH. Thamrin will be started from Bundaran HI MRT Station until National Monument (Monas)'s Fountain Roundabout," he said, Friday (7/27).

In order to support MRT construction, his side will implement traffic engineering based on the construction stages, as follows;

1. Stage 1.1 (July 24 - November 30, 2020)

a) Making a detour/widening Jalan MH. Thamrin in front of Gedung Sinarmas

b) Making a detour/widening Jalan MH. Thamrin on the eastern area starts from in front of Agency for the Assessment and Application of Technology (BPPT) Building until Bank Indonesia Building.

c) Making a detour/widening Jalan MH. Thamrin on the western area from in front of Energy and Mineral Resources Ministry (ESDM) up to Thamrin 10

d) Demolishing Bank Indonesia Transjakarta Bus Stop

e) Building temporary Transjakarta Bus Stop

2. Stage 1.2 (December 1, 2020 - March 30, 2021)

a) Construction site will use the road median and Transjakarta bus lanes along the area.

b) Bank Indonesia Transjakarta Bus Stop will be moved to temporary bus stop on the eastern side of Bank Indonesia Building and Wisma Mandiri

c) Transjakarta mix traffic lanes and regular lanes will be moved to the leftmost lane based on the temporary bus stop location

"During the Stage 1.1 period, one lane will be closed along the construction area. Then for Stage 1.2, detour or widening the eastern and western side of Jalan MH. Thamrin later can be used for traffic," he explained.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1036 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye902 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye541 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye446 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye379 personAldi Geri Lumban Tobing