Konstruksi MRT Fase II Dimulai, Dishub Lakukan Rekayasa Lalin
.
photo istimewa - Beritajakarta.id

MRT Phase II Construction Begins, Dishub Ready to Implement Traffic Engineering

Jakarta Transportation Agency (Dishub) implements traffic engineering on Jalan MH. Thamrin, Central Jakarta, due to Mass Rapid Transit (MRT) Phase II construction.

For the first stage of construction work on Jalan MH. Thamrin will be started from Bundaran HI MRT Station until National Monument (Monas)'s Fountain Roundabout

Through MRT Phase II construction project, MRT will expand and connect its lane from Bundaran HI MRT Station to Kota Tua which divided into 3 sections; CP 201, CP 202, and CP 203.

Jakarta Dishub Head, Syafrin Liputo conveyed, the construction will be started from Bundaran HI Station to Simpang Harmoni which called the CP 201 section.

MRT Phase II Construction will Be Postponed Until June 2020

"For the first stage of construction work on Jalan MH. Thamrin will be started from Bundaran HI MRT Station until National Monument (Monas)'s Fountain Roundabout," he said, Friday (7/27).

In order to support MRT construction, his side will implement traffic engineering based on the construction stages, as follows;

1. Stage 1.1 (July 24 - November 30, 2020)

a) Making a detour/widening Jalan MH. Thamrin in front of Gedung Sinarmas

b) Making a detour/widening Jalan MH. Thamrin on the eastern area starts from in front of Agency for the Assessment and Application of Technology (BPPT) Building until Bank Indonesia Building.

c) Making a detour/widening Jalan MH. Thamrin on the western area from in front of Energy and Mineral Resources Ministry (ESDM) up to Thamrin 10

d) Demolishing Bank Indonesia Transjakarta Bus Stop

e) Building temporary Transjakarta Bus Stop

2. Stage 1.2 (December 1, 2020 - March 30, 2021)

a) Construction site will use the road median and Transjakarta bus lanes along the area.

b) Bank Indonesia Transjakarta Bus Stop will be moved to temporary bus stop on the eastern side of Bank Indonesia Building and Wisma Mandiri

c) Transjakarta mix traffic lanes and regular lanes will be moved to the leftmost lane based on the temporary bus stop location

"During the Stage 1.1 period, one lane will be closed along the construction area. Then for Stage 1.2, detour or widening the eastern and western side of Jalan MH. Thamrin later can be used for traffic," he explained.

Linked News
Popular News indeks
  1. Jakarta Fair Kemayoran Begins, Hailing City’s 498th Anniversary

    access_time20-06-2025 remove_red_eye363 personDessy Suciati
  2. Pramono Ensures KJP will Continue to Be Distributed

    access_time26-06-2025 remove_red_eye299 personDessy Suciati
  3. Most Residents Satisfied with Pramono-Rano's Performance

    access_time25-06-2025 remove_red_eye294 personDessy Suciati
  4. Governor Pramono: Jakarta E-Prix 2025 in Ancol is Amazing!

    access_time21-06-2025 remove_red_eye266 personDessy Suciati
  5. Here are Parking Spaces around Lapangan Banteng for Jakarta's Anniversary

    access_time21-06-2025 remove_red_eye260 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik