 Pengerukan Lumpur Setu Babakan Sudah Capai 80 Persen

Mud Dredging Work in Setu Babakan Touched 80 Percent

Process of mud dredging work which carried out since July 2020 in Setu Babakan Lake, Srengseng Sawah, Jagakarsa, South Jakarta now has reached about 80 percent.

We dredge it to depth of 2 meters

South Jakarta Water Resources (SDA) Sub-agency, Mustajab conveyed, there was siltation in this 34-hectare lake. In order to optimize its capacity in rainy season, his side normalized it by dredging mud sedimentation from the lake.

"We dredge it to depth of 2 meters," he stated, Saturday (11/28).

SDA Uses Watermaster to Dredge Mud Sedimentation in Ria Rio Reservoir

In this dredging, his side deployed 5 heavy equipment on the south side. This work was estimated to finish in December.

"After being dredged, its capacity can be optimal thus it can reduce number of inundated locations in the region," he said.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1408 personFolmer
  2. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye847 personAldi Geri Lumban Tobing
  3. Commemorating Vesak, Jakarta Lights Up with Illumination of Jakarta 2026

    access_time30-05-2026 remove_red_eye649 personBudhi Firmansyah Surapati
  4. Seniors Participate in Pasti Bisa Berkarya at MRT Stations

    access_time02-06-2026 remove_red_eye596 personAldi Geri Lumban Tobing
  5. Krendang Fire Victims Receive Proper Support and Assistance

    access_time29-05-2026 remove_red_eye470 personBudhi Firmansyah Surapati